Which of the following components of a business continuity
plan is PRIMARILY the responsibility of an organization?s IS
department?

A. Developing the business continuity plan

B. Selecting and approving the strategy for business
continuity plan

C. Declaring a disaster

D. Restoring the IS systems and data after a disaster

Answer Posted / guest

Answer: D

The correct choice is restoring the IT systems and data
after a disaster. The IT department of an organization is
primarily responsible for restoring the IT systems and data
after a disaster at the earliest possible time. The senior
management of the organization is primarily responsible for
developing the business continuity plan for an organization.
They are also responsible for selecting and approving the
strategy for developing and implementing a detailed business
continuity plan. The organization should identify a person
in management as responsible for declaring a disaster.
Although IT is involved in all the other three components,
it is not primarily responsible for them.

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

WHICH OF THE FOLLOWING IS OFTEN AN ADVANTAGE OF USING PROTOTYPING GOR DYDTEM DVELOPMENT

2847


purchase orders issued to vendors have been authorized as per the authorization matrix

1095