You are a project manager for Laurel’s theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. The cost variance was projected using which of the following tools and techniques? A. Performance measurements B. Cost baseline measurements C. Computerized tools D. Performance reports
You are a project manager for Laurel's theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. You know all of the following are true regarding Cost Control except: A. Performance is monitored to detect variances B. Changes are reflected in the cost baseline C. Changes are monitored and reflected in the project scope D. Changes are monitored so that inappropriate changes do not get into the cost baseline
Which of the following might require rebaselining of the cost baseline? A. Corrective action B. Revised cost estimates C. Updates to the cost management plan D. Budget updates
You are working on a project to develop a new website for your company. You are monitoring results of the project to determine if they comply with standards set out during the Planning processes. You are also taking steps to eliminate unsatisfactory results. This might mean rework in some cases. Which process are you in? A. Risk Monitoring and Control B. Quality Control C. Integrated Change Control E. Scope Change Control
This tool and technique of Quality Control keeps errors from reaching the customer: A. Inspection B. Prevention C. Corrective action D. Performance measurement
Common causes of variances are a result of all of the following except: A. Random variances B. Predictable variances C. Special variances D. Variances that are always present in the process
You are a project manager in the manufacturing industry. You are using sample variance measurements to monitor the results of the process over time. Which tool and technique of Quality Control are you using? A. Statistical sampling B. Scatter diagrams C. Control charts D. Pareto diagrams
All of the following are true regarding Pareto diagrams and Pareto theory except: A. Pareto diagrams are histograms. B. Pareto diagrams rank order factors. C. A small number of causes create the majority of problems. D. Pareto diagrams use two variables.
You are preparing a diagram that plots two variables, the dependent variable and the independent variable, to see the relationship between the two elements. What kind of diagram are you using? A. Cause-and-effect diagram B. Control chart C. Flowchart D. Scatter diagram
Your project progressed as planned up until yesterday. Suddenly, an unexpected risk event occurred. You quickly devised a response to deal with this negative risk event using which of the following tools and techniques of Risk Monitoring and Control? A. Risk management plan updates B. Workarounds C. Corrective action D. Additional risk identification
You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Slowly but surely your programmers are taken off this project and reassigned to the executive director's hot new project. Which of the following type of project ending is this? A. Starvation B. Extinction C. Addition D. Integration
You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Your programmer’s are siphoned off this project to work on the executive director's hot new project. Which of the following addresses the purpose of Scope Verification in this case? A. It determines the correctness and completion of all the work B. It documents the level and degree of completion C. It determines if the project results comply with quality standards D. It documents the correctness of the work according to stakeholders' expectations
You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been canceled due to budget cuts. Which of the following is true? A. This project ended due to starvation because the funding was cut off B. This project ended due to integration because the resources were distributed elsewhere C. This project ended due to starvation because the resources were distributed elsewhere D. This project ended due to integration because the funding was cut off
All of the following are types of project closures or endings except: A. Addition B. Integration C. Verification D. Extinction
You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been completed and accepted. You've been given your next project, which starts right away. Which of the following is true? A. This project ended due to extinction because it was completed and accepted. B. This project ended due to integration because it was completed and accepted and the project manager moved on to a new project. C. This project ended due to addition because it was completed and accepted and archived into the company's catalog of available films. D. This project ended due to integration because it was completed and accepted.