ORA-16775: Target standby in switchover operation has
missing redo logs.
Answer / guest
Cause: The target standby database in a switchover operation
did not have all the redo logs from the primary database.
The switchover cannot continue in this case.
Action: Query SendQEntries to see what are the missing logs.
Make sure log transport service is functioning correctly. Do
some log switches on the primary and wait for the gap
fetching mechanism to re-ship all the missing redo logs.
Issue the switchover command again when there is no missing
redo logs on the target standby database.
Please add more information about this Error
| Is This Answer Correct ? | 0 Yes | 0 No |
RMAN-03002: failure of string command at string
NNO-00072: loading from region database
DGM-16946: Site "string" was not found
ORA-36804: (XSTBLFUNC02) The OLAP_TABLE function encountered an error while parsing the LIMITMAP.
TNS-04021: The SET command is unsuccessful for parameter string.
ORA-12995: no columns in partially dropped state
ORA-28261: CURRENT_USER can not be used in PLSQL Definer's Right procedure.
NNL-00037: Error number while sequencing through parameter table.
ORA-31669: Worker process string violated startup protocol.
ORA-32771: cannot add file to bigfile tablespace
RMAN-08583: channel string: archivelog copy complete, elapsed time: string
PCC-02020: Preprocessor error at line number, column number, file string: