What do you mean by ASAP methodology? Explain in detail
about the different phases / Stages in ASAP methodology?
I have an interview in immediate future so plzz help
me...Please reply asap... Urgent!!!! Waiting for your
response eagerly... Thanks in advance
Answers were Sorted based on User's Feedback
Answer / abhisek bhattacharya
SAP delivers the accelerated SAP(ASAP)methodology developed
by SAP to optimize the sucess of implementing the SAP
business suite.
ASAP streamlines the implementation by providing
templates,methods,tools and accelerators that have been
built on the success of thousands of previous SAP
implementation.
The ASAP methodology adheres to specific road map that
address the following five phases:
1.Project Preparation
2.Business Blueprint
3.Realization
4.Final Preparation
5.Go Live & Support
Is This Answer Correct ? | 18 Yes | 1 No |
Answer / katta gopichand
1) Project Preparation : where the SAP consultants try to understand the AS IS business process of the industry for which implementation is being done. The hardware and software requirements are analysed. Infact all the basic preparation is done at this stage.
2) Blue Print : After the AS IS study is made a TO BE process is evolved where in the client business is put in technically as to how it would be like in SAP. Blue is a binding between the implementor and Client. So, there is a sign off from the client on what is going to be done.
3) Realization : Here the blue print is configured on the system. For some processes where SAP cannot do as it is,like when there is a difference between AS IS and TO BE called a GAP , we use developers(ABAP) . The functional guys give the functional spec based on which the ABAP'rs prepare technical specs and fulfill the object ( may be reports, user exits, enhancements and so on). Also the unit and integration testing is done here.
4) Final Preparation : Here the enduser, core user training is completed on how he has to use the sap system. Master data uploads into the production server. In a way the system is getting for going live. And just before the go live date the data that needs to be put into sap is fixed and the remaining transactions of the business are recorded may be in a flat file or sometimes they are taken off so that upto date data in the production server is maintainted.
5) Go Live and Support : Here finally the SAP system goes live and followed by some support as agreed upon in the service level agreements .
Is This Answer Correct ? | 4 Yes | 0 No |
Answer / santhosh
1.Project Preparation
2.Business Blueprint
3.Realization
4.Final Preparation
5.Go Live & Support
Is This Answer Correct ? | 0 Yes | 0 No |
what is the relevance of vendor Tab in customer master and in which scenario you will use this tab?
What is the purpose of text item in item category?, How and why is it being used
Where do we can find pricing procedure indicator in sd ?
Hi,While doing PGI i am getting the error "filed selection for movement type 601 / account 89500 differs for customer goods movement (015)". I am trying to solve but coulnd't. Please get me the solution. Regards Naga
In Which scenario we can use different pricing procedures? Please explain with an example.
after billing what are the documents will be generated?
Even after Rebate agreement validity periods finish and the status is showing D completed still acuurals are calculating the accurals..for eg validity periods are finished at 2011 when we create billing document is creating in 2012 still accurals are calculating, where might be went wrong
Explain what is the difference between milestone and periodic billing?
Can you have many clients in your project? if yes tell me . If no why? Can you have many compnay codes if your company is having many business units? I have an interview in immediate future so plzz help me...Please reply asap... Urgent!!!! Waiting for your response eagerly... Thanks in advance
In a scenario where credit check is active for all customers and company wants to exclude a customer from credit check on a special case, how to do this?
How to know that customer has paid the bill? OR what is the procedure to make payment against a bill?