What is meant by MRP Type and lot sizing?
Answers were Sorted based on User's Feedback
Answer / subramanian
It is procedure that you set in the system on how the
Material is planned
Reorder Point
Seasonal requirement
Replenishment
Vendor Managed
Forecast Based
Master production Scheduling
Lot size :
You can define your requirements (to be produced or
Procured) in terms of Weekly, Monthly, Qty based, Maximum
Replenishment
Is This Answer Correct ? | 28 Yes | 7 No |
MRP type-
Key the determines wether and how the material is
planned.you have the following options.
-manual re-order point
-automatic re-order point
-fore-cast based planning
-material requirement planning
-master production scheduling.
LOT-SIZE-
Key that determines which lot size procedure, the system
uses with in material planning to caleculate the quantity
to be procured or produced.
Is This Answer Correct ? | 19 Yes | 5 No |
MRP TYPE:
A key that controls the mrp procedure(mrp,re-order point,forecast based,time phased planing)used for planning a material.
Lot sizing:
A procedure in material requirement planning used to calculate orders and production quantities.
there are three groups of procedures exist for calculating the lot size.
1. static lot sizing
2. period lot sizing
3. optimizing lot sizing
Is This Answer Correct ? | 13 Yes | 6 No |
Explain the 'accounting' side of gr?
What are the industry-specific solutions available in mysap?
What is purpose of zgr based invoice verification in purchase order?
while creating inforecord system is asking 2 enter required entry at planed delivery time,entered a number but it is not accepting HELP ME plzzz
What is mysap erp? What business components can it be classified into?
"only 0.000 pieces are available" what does it mean during goods issue??
What do you understand by posting period?
What is FRC and JIT in scheduling agreement?
What is meant by access sequence? When it is used?
Where is the header level and item level data saved in a po?
State the importance of the vendor evaluation in the purchase department?
What are the data in the mm module that are maintained at the company code level?