How to calculate WIP in PS for all wbs pertaining to that
particular project? Any specific T code in ECC 6.0?
Answers were Sorted based on User's Feedback
Answer / deepa
KKA2 for calculating result Analysis;
KKAJ - for calculating WIP
Is This Answer Correct ? | 16 Yes | 2 No |
Answer / m t haque
KKA2 and KKAJ both do the same thing (RA and WIP calculation terms are used interchangeably) only difference is KKA2 is for individual processing while KKAJ if for collective procesing
Is This Answer Correct ? | 4 Yes | 1 No |
Answer / p.chaithanyavikram
HI All
Through T-code KKA2, Result Analysis we have to calculate the WIP (Work In Progress)
Is This Answer Correct ? | 0 Yes | 0 No |
What does a processes ensure?
What does scope management involve?
Difference between validation & substitution?
What are settlement rules?
explain unit costing
List different types of time profile
Explain wbs?
explain settlement rules
What is risk impact and probability?
How do you estimate in the three point estimating method?
What is the menu path & t. Code for defining special characters for projects?
Can you explain project life cycle?