what are the costing parameter ?
Answers were Sorted based on User's Feedback
Answer / balarama boddeti
Hi,
The costing Parameters are the following
Work center : Activity types and the formulaes,cost center
Routing : the time ,activity types
In Production order dependent parameters we are defining
the Variant ,result analysis key,settlement profile
In the controlling i.e in KP 26 we will be defining the
rates per hour depending on the rates it will reflect the
cost caluculating from the routing..
Balaram
Is This Answer Correct ? | 22 Yes | 2 No |
Answer / fareed ansari
Yes it is more or less correct
More precisely, costing parameters are
1) Routing: which delivers activity price & time
2) BoM: which is the contributor of standard material cost
against an order
3) Cost Centre: which is contributor unplanned material
issues against the production of FG/SFG.
Is This Answer Correct ? | 13 Yes | 3 No |
Answer / shib shaw
I/P & O/P Plan Cycle .
Work center : Activity types and the formulaes,cost center
Routing : Activity Price Calculation .
BoM: which is the contributor of standard material cost
against the Product in Production order.
Cost Centre: Production Cost Center mapped in Work center .
Indirect Cost Center the value of CC which is Updated in
Product through Assessment Cycle .
which is contributor unplanned materialissues against the
product.
Is This Answer Correct ? | 0 Yes | 3 No |
What is sap pp?
Explain schedule margin key
Can you dispatch capacity for a single work center
What is special procurement & tell one special procurement briefly
We have two storage locations are ‘0001’ and ‘0600’. Default storage location in process order is always ‘0001’ what determines this default location?
What is a ‘work center’ in pp?
Tell some sop
I have created an order type “ZYC6”, how I know that which types of order it is like process, production or SD order?
How do you get the system to update this value from the routing?
Explain the mrp group and their uses.
What are the production process in sap?
One component we can assign to workcenter at routing