how cubic feet cement,sand,aggregate required for 1 cubic feet
ratio=1,1.5,3
Answers were Sorted based on User's Feedback
Answer / mohammed aijaz hussain
Volume of concrete = 1 cu.ft.
Volume of Dry concrete = 1.5 X 1 = 1.5 cu.ft.
Volume of cement required = 1/ 5.5 X 1.5 = 0.273 cu.ft.
= 0.22 Bag = 11 kg.
Volume of sand required = 1.5/5.5 X 1.5 = 0.41 cu.ft.
Volume of aggregate = 3/5.5 X 1.5 = 0.82 cu.ft.
| Is This Answer Correct ? | 19 Yes | 8 No |
Answer / ratheesh
cement = 7.5 kg
sand = .0076 m3
Aggrigate = .015 m3
| Is This Answer Correct ? | 16 Yes | 9 No |
Answer / bharathi
cement - 8.22 Kg
Sand - 0.428 m3
20mm BM- 0.856 m3
| Is This Answer Correct ? | 4 Yes | 1 No |
Answer / arunkumar
cement = 3 kg
sand = 0.75 band
20mm metal =1 band
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / darshandachchu@gmail.com
cement=403.5kg
fa=.42cum
ca=.84 cum
| Is This Answer Correct ? | 2 Yes | 2 No |
Answer / r.suresh
cement= 11kg
sand = .012cuft
aggregate=.024cuft
| Is This Answer Correct ? | 9 Yes | 11 No |
Answer / n.rajeev
sand = .012cft
coarse aggregate = .024cft
cement = 17.28 kg
| Is This Answer Correct ? | 6 Yes | 8 No |
Answer / v.purushotham
Coarse aggregate: 0.96 cu.ft
sand : 0.48 cu.ft
Cement : 13.06 cu.ft
| Is This Answer Correct ? | 1 Yes | 3 No |
1. How do you handle non-productive team members?
Which stone is best for wall construction Laterite Stone or Cement Blocks
The relation between cube strength & cylinder strength because––
what is plum & mass concrete?
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
how to calculate quantity of steel in a slab , coloumn and beam
1 Answers JSW, Om Sai Builders,
dialation means
Pls. help. If a contract was awarded to a contractor in april 2012 with steel & cement base price as rs. 45/kg & 250/bag. Now in oct. 12 steel cement price becomes 55/kg & 290/ bag. How escalation will be calculated? Pls. tell complete calculation Regards,
How to distinguish that the soil is clay, silt, sand & murrum at site. (just by looking at it with out doing the sieve analysis test??
extra how much quantity need to fill the actual excavated quantity.
Requirement of cement, and steel 1:2:4 ratio concrete in 1128 Sqft area(Cement No of bags, steel in Kgs)
Quantity of cement in kgs for different proportions and different thickness in plastering work per 1 sq.m. And how to estimate this quantities.
2 Answers Al-Jaber, IVRCL, L&T,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)