how cubic feet cement,sand,aggregate required for 1 cubic feet
ratio=1,1.5,3
Answers were Sorted based on User's Feedback
Answer / mohammed aijaz hussain
Volume of concrete = 1 cu.ft.
Volume of Dry concrete = 1.5 X 1 = 1.5 cu.ft.
Volume of cement required = 1/ 5.5 X 1.5 = 0.273 cu.ft.
= 0.22 Bag = 11 kg.
Volume of sand required = 1.5/5.5 X 1.5 = 0.41 cu.ft.
Volume of aggregate = 3/5.5 X 1.5 = 0.82 cu.ft.
Is This Answer Correct ? | 19 Yes | 8 No |
Answer / ratheesh
cement = 7.5 kg
sand = .0076 m3
Aggrigate = .015 m3
Is This Answer Correct ? | 16 Yes | 9 No |
Answer / bharathi
cement - 8.22 Kg
Sand - 0.428 m3
20mm BM- 0.856 m3
Is This Answer Correct ? | 4 Yes | 1 No |
Answer / arunkumar
cement = 3 kg
sand = 0.75 band
20mm metal =1 band
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / darshandachchu@gmail.com
cement=403.5kg
fa=.42cum
ca=.84 cum
Is This Answer Correct ? | 2 Yes | 2 No |
Answer / r.suresh
cement= 11kg
sand = .012cuft
aggregate=.024cuft
Is This Answer Correct ? | 9 Yes | 11 No |
Answer / n.rajeev
sand = .012cft
coarse aggregate = .024cft
cement = 17.28 kg
Is This Answer Correct ? | 6 Yes | 8 No |
Answer / v.purushotham
Coarse aggregate: 0.96 cu.ft
sand : 0.48 cu.ft
Cement : 13.06 cu.ft
Is This Answer Correct ? | 1 Yes | 3 No |
How to calculate the steel for 392c.meter*450c.meter rcc slab
how can we calculate steel value, depending on load
State the type of roads and compare the advantages and disadvantages?
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
Define What are the reasons for geotechnical site investigations in Uganda?
Explain what is alternate bid?
What is the zero value in quantity surveying
it is a corrected question." make a list of engineering property(properties) of soil.
0 Answers AAI Airports Authority Of India, DLF,
How to calculate the shuttering materials i.e MS sheet,Props,Acrow Spans,2'x3' Runner,4'x3' Runner & beam plywood bottom, sides in thumb rules in slab area
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
What is cement-concrete ratio ?
Whats be the minimum foundation depth of multistoried building as per height of building in individual footing?