What is the cement content for 1m3 of
M20,M25 concrete?
Answers were Sorted based on User's Feedback
Answer / sara
M20=1:1.5:3
Dry volume of concrete in 1cum=1.54
Cement Quantity=1.54/(1+1.5+3)
=0.28cum
=0.28/0.035=8 bags
=0.28*1440=403.2kg
same way we can calculate M25 cncrete
Is This Answer Correct ? | 28 Yes | 10 No |
M25
Cement =320 kg/cu.m
fine aggregate= 751 kg/cu.m
coarse aggregate =
20 mm = 977 kg/cu.m
10 mm =380 kg/cu.m
w/c ratio = 0.43
quantity of water= 138 liter
M20
Cement =290kg/cu.m
fine aggregate= 696 kg/cu.m
coarse aggregate =
20 mm = 1029 kg/cu.m
10 mm =400 kg/cu.m
w/c ratio = 0.5
quantity of water = 145 liter
Is This Answer Correct ? | 12 Yes | 9 No |
Answer / imran
54% add for wet dry volume and wastage .
dry volume -1x1.54= 1.54m3 m 15(1:2:4)
so, cement 1/7x1.54= ? nd then 1/0.0347x?=? bsgs
sand-2/7x1.54=? m3
coarse agg.-4/7x1.54=?m3
Is This Answer Correct ? | 6 Yes | 4 No |
Answer / dalchands
M20=1:1.5:3
Dry volume of concrete in 1cum=1.52
Cement Quantity=1.52/5.5
=0.28cum
=0.28/0.035=8 bags
=0.28*1440=403.2kg
M25=1:1:2
Dry Volume = 1.52/4
Cement = 570.00 kg
Is This Answer Correct ? | 6 Yes | 6 No |
Answer / mohammedazharuddin
QUANTITY OF CEMENT IN 1CUM FOR M20,M25 IS 320KG AND 340KG
NO.OF BAGS = 6.2 FOR M20 AND 7 FOR M25
RATIO OF M20,M25 = 1:1.5:3,1:1:2
Is This Answer Correct ? | 14 Yes | 15 No |
Answer / senthil kumar
M10-3.4nos of bags of cement
M15-6.2
M20-6.8
M25-7.5
M30-8.5
M35-9
M40-10
Is This Answer Correct ? | 2 Yes | 8 No |
Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?
what are the CAD software versions you have used?
12 Answers ERA, IES,
What is the quantity of cement in mix m20 concrete?
what is the weight of concrete for 1 cum?
15 Answers Dhenu Infrastructure, L&T,
what is the significance of bending moment in a structure?
what is tension column?
0 Answers Wah Engineering College,
Respected Sir, I am from a hilly place called Darjeeling ,I have constructed house of 9 column out of which 4 of the column is under water , i have put rcc slab on top and on top of the rcc slab i have construced two room house with bricks and light roof , now i am planning to change the light roof with rcc slab for the two room, my main concern is will the column under water will hold the load of the new rcc slab coz it already 10 to 12 yrs old , i dont know what to do , can u advice me regarding this matter, weather to leave the upper floor roof light or make it rcc slab.(If i put the slab , it will require 45bags of cement and u calculate how much of steel and sand and pebbles) thanks with regard Anand
Cemen-1 Fine agr.-2 Core agr.-3 calculate for per 100 qube feet (qubic feet wise)
what is the problem not getting 7 days slab cycle in Mivan formwork? what is the output of mivan carpenter per day?
bar bending schedule?
WAS PUMP MODEL WXB DESIGNEDIN ACCORDING API 610 STANDARD?
suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?