How to calculate the quantity of brick or mortar in m3.
like in 1m3 brick =....no.
.......mortar=....m3
Answer / sudar
The size of the modular brick is 190 X 90 X 90
Mortar Thickness is 10mm
Assume required brickwork volume is 1 cubic metre (m3)
Volume of bricks with mortar
Volume of 1 brick with mortar = 200 X 100 X 100 ( 10 mm mortar thickness on all sides)
= 0.2 X 0.1 X 0.1
Volume of brick with mortar = 0.002 Cum (m3)
Therefore, Number of bricks required for 1 cubic metre = 1/0.002 = 500 No.s
Volume of bricks without mortar
Volume of 1 brick without mortar = 190 X 90 X 90
= 0.19 X 0.09 X 0.09
Volume of 1 brick without mortar = 0.001539 Cum (m3)
Volume of 500 bricks without mortar = 500 X 0.001539 Cum
Volume of bricks without mortar for 1 cum = 0.7695 Cum (m3)
Therefore,
Required amount of cement mortar = 1 Cum – Volume of bricks without mortar
= 1 – 0.7695
Required amount of cement mortar = 0.2305 Cum (m3) (Wet Condition)
Dry volume of a mortar = 0.2305 cum X 1.33 = 0.306565 cum
We Assume the mortar ratio is 1:6 (1 part Cement & 6 Part Sand = 7 Part)
Required amount Cement quantity in brickwork = 0.306565 X 1/7 X 1440 kg
Required amount Cement quantity = 63 Kg = 1.26 bags (50 Kg bag)
Required amount of Sand = 0.306565 X 6/7 = 0.26277 Cubic metre (m3)
Therefore, For 1 cum of brickwork, we need
500 Numbers of bricks
63 kg of cement
0.263 m3 of sand.
| Is This Answer Correct ? | 0 Yes | 0 No |
Are you comfortable with formal design concepts in the home furnishings area?
What is the different kinds of support?
what are the basic parameters considered in designing a pavement?
Does brick grows bigger every year?
how many average of shuttering in one cubic meter concrete
please know me that required quantity of cement , sand , water and bricks for 1 cub meter of brick work
What is the difference between stress and pressure
1) what do you mean by rolling margin of steel ? 2)pls. tell the cut length formula of stirrups as per IS codes(take out cut length for a beam of 600*300mm with 40mm cover all sides)? 3)what is the multiplying factor of painting for sand faced plaster? 4)if your footing is of size1.9*1.6m . what quantity of length and width you will excavate means what extra margins you will allow as per IS codes in billing?
apparatus of soundness test of cement
if L*B*H = 20 then direct no of bricks =20 *500
How to calculate the thickness of the rcc slab?ll u pls tell the formula?
Wat is the optimum value of tensile strength of concrete after 28 days?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)