Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


Generally in which location ( JB or IO card or DCS) the
thermocouple compensation is done.Also where they measure
the atmosphere temp ( for compensation) in JB OR DCS panel?
How they compensating that atmosphere temp? is any circuit
for that ( like in rtd wheatstone bridge)?

Answers were Sorted based on User's Feedback



Generally in which location ( JB or IO card or DCS) the thermocouple compensation is done.Also whe..

Answer / satish tumbare

Actually compensation is done in Transmitter.Transmitter
have one IC which cslculate ambient temperture.
2.If output of thermocouple is mV then compensation is done
in DCS .
In DCS one temperture sensor is connect to Analog
input card .This sensor measure room temperture using this
temperture we can calculate T/C compensation.

Is This Answer Correct ?    5 Yes 0 No

Generally in which location ( JB or IO card or DCS) the thermocouple compensation is done.Also whe..

Answer / carl_ellis

Cold junction compensation (CJC) is done at the point where
the thermocouple wire or thermocouple extension wire
connects to the thermocouple input, either an I/O card, a
temperature transmitter, or a thermocouple input on a
recorder/controller/indicator/alarm. RTD's do not need
CJC. Thermistors do not need CJC.

The purpose of CJC is to measure the temperature of the
termainal connection block with respect to the freezing
point of water (because that is the 'cold junction' and the
national standard thermocouple tables are referenced to) a
cold junction at the freezing point of water) and add that
value to the temperature value determined by the EMF/mV
output of the thermocouple.

The temperature of the terminal connection block is affected
by ambient, room, or atmospheric temperature but is also
affected by the heat generated by the device's electronics,
other electronics in close proximity, and whatever cooling
the installation provides. Because all of those factors can
vary in temperature, the CJC involves measuring the
tempeature of the (terminal) connections.
Temperature-sensing ICs, thermistors, and RTDs are used for
CJC measurements. Thermocouples cannot be used for CJ
measurement.

So the answer is that the CJ measurement is made at the
thermocouple input, presumably the I/O card or temperature
transmitter, never at a junction box.

The actual temperature calculation, measured T/C EMF plus
CJC, can be done on the I/O card or in the 'system', a PLC,
temperature transmitter, controller, DCS, whatever,
depending on design.

CJ should not measure room temperature or atmospheric
temperature (although some poorly designed thermocouple
devices do so); CJ should measure the terminal temperature
where the thermocouple wires connect to the I/O. A
temperature transmitter measures the CJC in order to do the
calculation for temperature.

There are special techniques for CJC for high accuracy
calibration involving an ice bath, but industrial devices
use integrated CJC.

Tell 'em Carl sent you.

Is This Answer Correct ?    3 Yes 0 No

Generally in which location ( JB or IO card or DCS) the thermocouple compensation is done.Also whe..

Answer / phani

the cable termination for the thermocouple is thermocouple-JB-temp transmitter-IO cord(DCS),in this cable termination compensation ll be done in JB only.

Is This Answer Correct ?    3 Yes 1 No

Post New Answer

More Instrumentation Interview Questions

send me HPCL paper

6 Answers   HPCL, Shuiba Hotel,


Explain an adaptive / self-tuning controller’s major draw card.

0 Answers  


why use 4-20mA in the field of instrumentation?

8 Answers  


what is the difference about HART, and 4-20mA signal?

8 Answers  


Explain Three way boiler.

2 Answers   L&T,


i m passed my engineering in 2010 in instrumentation and control engineering. my question is can i apply for software jobs or vacancies.??????????? plz give me answer soonnn......

2 Answers  


how can i check vortex shedder bar it is ok? if there is ohms condition are shown correct?

0 Answers   Chevron Phillips,


Hello friends i need check lists of different instruments during the Erection and commissioning in thermal power plant.Please help me.My Mail id is naba02222@gmail.com/naba02222@rediffmail.com Thanks Nabakishore Biswal

1 Answers  


what is the meaing of calibration curve?

3 Answers   HCL, Honeywell,


thru which signal does µP communicate with memory

3 Answers  


what is diffrence between analog card and digital card in plc.how analog card work,Please explain in detail.Please send it on abhi_vyas@sify.com

6 Answers  


how to solve temperature error in compressor?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)