why the under of transformer platform is filled with rock stones.

Answers were Sorted based on User's Feedback



why the under of transformer platform is filled with rock stones...

Answer / rk

TO REDUCE THE FIRE HAZARD DURING OIL LEAKAGE OR OIL
SPILLOVER DURING ANY UTWANTED SITUATIONS FOR INSTANCES SHORT
CKT. INSIDE TRANSFORMER. OIL IS FLAMMABLE IN NATURE.

Is This Answer Correct ?    21 Yes 6 No

why the under of transformer platform is filled with rock stones...

Answer / rajeshsan

There are many reasons for using gravel stones of 60mm size below transformer. Few are:-

1. During oil spillage from transformer or during sprinkler system act the water draining from soak pit it will be easier.

2. To avoid the grown of grass and entry of animals etc.,

3. To reduce the step potential

You can please refer the NFPA 850 for details.

Is This Answer Correct ?    14 Yes 3 No

why the under of transformer platform is filled with rock stones...

Answer / santhosh (saint-gobain)

1. Avoid water stagnent under transformer,
2. Vibration absorption,
3. Stones having no conductivity..

Is This Answer Correct ?    2 Yes 2 No

why the under of transformer platform is filled with rock stones...

Answer / saikrishna

To decrease the contact from earth

Is This Answer Correct ?    0 Yes 0 No

why the under of transformer platform is filled with rock stones...

Answer / m.kumaran

because reduce the step potential while short circuit timing

Is This Answer Correct ?    8 Yes 10 No

why the under of transformer platform is filled with rock stones...

Answer / suresh babu

first to prevent the stagnent of water under the transformer
second vibration withstand
third low resistivity i mean rock stones forms low
resitivity path

Is This Answer Correct ?    2 Yes 7 No

why the under of transformer platform is filled with rock stones...

Answer / baljeet singh

To reduce the short circuit current when fault occurs in transformer

Is This Answer Correct ?    3 Yes 10 No

why the under of transformer platform is filled with rock stones...

Answer / raghu

The stones will absorb the vibrations from the transformers
and other switch gear equipemts..

Is This Answer Correct ?    5 Yes 14 No

why the under of transformer platform is filled with rock stones...

Answer / talluri

Rock will protect substation from electrical damages

Is This Answer Correct ?    0 Yes 12 No

why the under of transformer platform is filled with rock stones...

Answer / shahul

To avoid the snake and other insect enter inside the
transformer structure and also avoid water flooding
under the transformer during the rainy season

Is This Answer Correct ?    4 Yes 20 No

Post New Answer

More Electrical Engineering Interview Questions

Witch do depand of Power factor and theory of power factor?

0 Answers  


What is the output of 25 kva 11/.4 kv transformer in kw ? Plz generalized it...

3 Answers   NTPC,


How to apply 'c' license and also explain what is difference between 'c' and 'b'license.i am also working in one of the private company.i have finished my diploma in 2014 .i have already finished in ITI electrician course.....

0 Answers  


how to meas-our losses for L.T & H.T

0 Answers  


what is the basis for selection of Protection CT class ? How anyone can decide whether to go for 5P10 or 5P20 ?

3 Answers  






is there any current flows in our body?

4 Answers  


in three phase it represented by R-Y-B.what is full form of R-Y-B.

11 Answers   Sun Pharma, TCS,


What will be the impact on motor performance if a LT motor is rewound with changed motor winding data as given below:- Original winding data: total 04 wires = 02 wires of 17 SWG + 02 wires of 16.5 SWG. Changed Winding data: total 03 wires of 15.5 SWG wire size Motor rating: 160KW, 740RPM, 415V, ID FAN application. Normal Running Current = 95% of FL Current.

0 Answers   NFL,


we all know that corona is nothing but ionization of air around the conductor and there by allowing current to pass through ionized air.but we are not getting any short circuit in between the respective phases though the air turned as a conductive media between them??

1 Answers   Siemens,


What are the different protection systems used to protect the transformer internally and externally?

16 Answers  


Why reactors use before incoming of ac vvfd drive?

0 Answers  


We normally make oil soak pits under Transformers. Oil from soak pit goes to collection pit. We provide granules/pebbles under transformers. My question is weather granules/ pebbles to be filled in soak pit or not? if yes upto what level?

0 Answers   Bhel,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)