Have idea about variant configure
Answer Posted / dd_qm
Variant configuration used basically in the following cases:
1-when the product range is very complex.
2-Material planning are done as per Make To Order.
3-Material must be batch managed.
5-During creation of sales order the sales guy put all the material specifications by using characteristics.
6-The values entered against characteristics in Sales Order are considered during material planning @ sub floor level.
7-At sub floor level the production person has a clear idea about the customer requirement , hence better customer satisfaction.
8-Main advantages in case of VC is no need to maintain a huge list of material codes as per material specification.
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
How are time management and payroll are integrated?
What is Production scheduling Profile and use of it?
How can you create production order without routing and BoM?
Difference between standard cost and variable cost.
In sap-pp what are the costing parameters?
How requirements( pir, sales order, customer requirement) are reduced after they are produced?
What is the use of stock requirement list?
What is the uses of production scheduling profile and what the configure have you done current project
What is plm (product lifecycle management) in sap pp and what is the use?
What is the difference between the fixing type 1, 2, 3, 4?
what is group bom? Is it possible to attach the drawing for a material to bom? How?
Can’t one material be assigned to more than one operation in a routine?
What is the planning time fence?
What are dynamic actions? Give a few examples. What are it’s you used in them?
How can you get planned orders scheduled so that you can do capacity leveling ?