Onsite percentage wastage of Concrete, Rebar, Blockwork/Brickwork, Plaster, Floor tiles ??

Answer Posted / karthik rajendren

3% for Concrete & rebar
5% for Brick/Block Work,Plaster& Tile

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Is there any course for billing available in Mumbai? If yes then please mail me the details..

1818


can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?

2071


What is labor and material payment bond?

641


how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you

1513


what is constat for brickwork

1691






can u plz send me ntpc placement papers(civil engineering) at mohit_verma21@yahoo.com

2061


For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)

1529


what is civil enginnering & what you need of this course?

1800


Who built the sears tower?

643


What is the FE 250 structural steel of 8mm tk plate testing sample intervals with IS code or international code?

1854


 Which Types Of Bricks ? 

2525


What is the ideal size of the living room ranges from small to large size?

666


what is SDLC ?and write a 'c'program for to swapping the three numbers?

1403


For the symmetrical continuous beam shown in figure, Prestressed with a force P = 1500 KN along parabolic curve as shown, compute the extreme fiber stresses over the central support for the uniformly distributed load of 24 kn/m. Use load balancing method.

1711


strength of bitumen concrete with 80-100 & 60-70 grade bitumen

1672