Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answer Posted / r. dilli babu
Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will be
=h/3(A1+A2+Sq root of A1square+A2square)
=((.5-.15)/3)(.09+3.4+(sq root of(.09 square + 3.4 square)))
=.116(3.49+(sq root of (11.5681))
=.116(3.49+3.401)
=.116*6.891
=.799 cum
Is This Answer Correct ? | 8 Yes | 4 No |
Post New Answer View All Answers
what is constat for brickwork
pls mail some more tecnical qustions at msaranya2610@gmail.com
it is a corrected question." make a list of engineering property(properties) of soil.
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
how many running meters in one kilogram of 4mm pvc coated chainlink fencing
How do you determine specific gravity of cement?
how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?
Explain the water bound macadam roag
What Are The Different Type Of Slump Test Indications?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
is there any influence of water(used for mixing of concrete) on a weight of harndend concrete.
What is limit state method and working stress method and ultimate method
Advantage of Aluminum form work in terms of activities can be skip and cost too
How do we test on design and style in a software?