what mean by valuated stock,non valuated stock?.
which cotagiri u r using in po&pr

Answer Posted / nmpandey

In Valuated stock every material in stock is managed on a
both a quantity basis and a value basis. The monetary value
of each quantity of material is calculated separately. while
non valuated material is maintained as per quantity and not
on the basis of its value.

Is This Answer Correct ?    21 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

a new comer joined in ps consultant role, whats his first job and duty? how he can explain the project details to others? i requesting all the experienced consultants please post the your real time faced attitude and job based problems for getting the morality from you people. please post the answers

2589


Can revenues be linked with activities?

598


What is the organizational structure of ps module?

577


What setting does ntw scheduling contains? Where are these settings done (menu path)?

535


What is the menu path & t. Code for defining special characters for projects?

731






What is project coding mask?

622


You want to set the options for capacity report cm01. How would you do that?

573


How and where do you control the budget for the project & what is the menu path?

581


Where do we define time profiles?

611


What do activities, ntw, wbs represents?

623


Explain planning profile.

574


You want to lock two wbs items say overheads and other expenses so that the user can not release pr. How would you do that?

676


You want to update the progress in wbs elements. How would you do that?

622


How do you perform user authorization in sap system using grc access control?

599


What is the difference between validation & substitution?

558