How would we calculate the no of earthing pits required
for motor /panel

Answer Posted / shreenidhi

There is no general rule to arrive at the exact no of earth
pits.But discharging of leakage current is certainly
dependent on the area/cross section of the material.In
other terms for any equipment the earth strip size is
calculated on the current to be carried by that strip.First
the leakage current/current to be carried is calculated and
the size of the strip is determined/sized.For most of the
electrical equipments like Transformer,DG set etc.,the
general concept is to have 4 nos earth pits.2 nos for body
with 2 seperate strips and the pits shorted and 2 nos for
neutral with 2 seperate strips and the pits shorted.The
general rule is that for neutral ,the strip size should be
capable to carry neutral current of that equipment & for
body the strip should be capable to carry half of neutral
current.For example for 100kVA transformer,the full load
current is around 140A.The strip connected should be
capable to carry atleast 70A(neutral current)which means a
strip of GI 25x3mm should be enough to carry the current
and for body a strip of 25x3 will do the needful.Here I am
taking the strip size that is generally used as
standards.However a strip with lesser size which can carry
a current of 35A can be used for body earthing.The reason
for using 2 earth pits for each body and neutral and then
shorting them is to serve as back up.If one strip gets
corroded and cuts the continuity is broken and the other
leakage current flows throgh the other run thery by
completing the circuit.Similarly for panels the no of pits
should be 2 nos.The size can be decided on the main incomer
breaker.For example if main incomer to breaker is 400A,then
body earthing for panel can have a strip size of 25x6 mm
which can easily carry 100A.

Is This Answer Correct ?    9 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the differance between 2 dc motors of armature voltage 660 v and 440 v?

1553


How to decide CT & PT ratings for a given transmission line carrying some rated voltage?

1890


What is main cause of cable's terminal point burned in Lug on high temperature although lug and cable selection is ok as per stantard and also tightness is ok as per situation. so please take in deep and tell correct answer thanku.

7409


When we giving the 3 phase supply to ups system how to coming netural?

1648


how harmonics generated in induction furnance? how minimise it?

1534






Do you know what is dry-out test in x'mer

2218


What is minimum permicible value of leackage current for LT Panle when applying voltage up to 3 KV for 5 Minuits?

1717


Why is negative feedback invariably preferred in closed loop system?

1759


what is the meaning of osr in transformer.

1549


What Normal(Tangent) towers and Tension(Cut-point) Towers?

5233


Explain RLC circuit?

742


Why we find the sensitivity for the CT's to check?

1421


What is cross over distortion? How it can be eliminated?

784


why and where we use early make & late break contacts in protection?

7637


hi this is hema can anyone mail me previous years questions for the APPSC-A.E.E (in electrical stream.) ......thank u.

1467