You are the test manager starting on system testing. The
development team says that due to a change in the
requirements, they will be able to deliver the system for
SQA 5 days past the deadline. You cannot change the
resources (work hours, days, or test tools). What steps
will you take to be able to finish the testing in time?
Answer Posted / neelima
1. priortise the tests based on the requirements
criticality,complexity, end user stressed .
2. check with the developers about what requirements are
going to be changed and how many tests are going to be
effected due to that.
3.check with the project manager to defer any of the
functionality testing for later .
4. check with the developers how thorough that their
modules are tested .
Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
Any one please can u tell me what is composer? An interviewer asked me do u have experience in Composer? its urgent.
What does 100% statement coverage mean?
What is date driven testing?
please anyone let me know the -ve testing of Excel sheet?
what is the use of l10n testing?
What is bug release?
Explain the difference between alpha testing and beta testing.
Can any one explain me about hybrid integration testing? and what is interface in integration testing? thanks in advance...... regards, MurthySharma.Manchella
Katari your questions was really helpful could you please send the questions and answers with them . Can anyone sends the top 30-40 question and answers for the interview purposes
qtp9.2 and qtp10.0 difference
What is a failure?
1)can u tell me, what is the roles and responsibles for database tester in DB testing from requirement stage to UAT stage....2) what are the i/p documents he wants and who wil give the i/p docs. to DB tester.and tell me what exactly db test case means what?
How to test an Scheduled event? For ex: in an investment banking application, the scheduler will create an equity anbd user has nothing to do but tester has to test if the instrument is created properly or not?
What do you understand by usability testing?
write test condition for testing SMS service of a mobile phone maximun length is 100 character while sending and 80 character for receiving write test scenarios do not write test cases