how to determine capacitor bank capacity of one plant..

Answers were Sorted based on User's Feedback



how to determine capacitor bank capacity of one plant....

Answer / thowsif_emerson

Hi If We know the plant:-

Input Initial Power Factor:-
Input Desired Power Factor:-
Input Load KW :-

Then we can cal the Required Kvar i.e capacity
of Capacitor bank...

Is This Answer Correct ?    25 Yes 2 No

how to determine capacitor bank capacity of one plant....

Answer / pichumani

As a thumb rule, 1/3 (30% appx.) of your KVA demand shall
be the KVAR requirement of your plant.

Is This Answer Correct ?    2 Yes 1 No

Post New Answer

More Electrical Engineering Interview Questions

How to find out kvar from any particular load capacity give a formula

3 Answers  


Circuit diagram of tube light without starter using electrical choke

0 Answers  


can anybody give me current carrying capacity of cables e.g size of cable in sq.mm & its current capacity both alluminum & for copper

4 Answers  


1. what is usage for power factor in industries?? 2.why we need to monitor power factor??

4 Answers   Havells,


why is fan rotating slow speed, what is the problem?

4 Answers  






Is 3C x 2.5 Sqmm Cable can withstand 40Amp Starting current? If Yes then specify your ans.

2 Answers   NTPC,


How to increase solar cell efficiency ?

1 Answers  


what is difference between short ckt and overload?

6 Answers   Siemens,


what is use of stater and choke in tube light.?

2 Answers   Aditya Birla,


what is difference between cpp electrical system and refinery electrical system

0 Answers  


What is the difference between AC Drives and DC Drives?

14 Answers   College School Exams Tests, La-Gajjar Machineries, LG, Schneider, SMEL,


Please clarify, 1. Is it required to lay two runs of GI wire along with Armoured LT cable if it is laid between one big mains (63Amps TPN SDF) to small main (32A TPN SDF) with proper glanding termination? 2. If the armoured cable with proper glanding is laid from DB to CNC machine, is it required to run two runs of body earthing to the Machine from DB? 3.If the armoured cable with proper glanding is laid from Substation to Hangar, distance is approx. 100 mtrs, is it required to do earthing at shop area though the primary termination at substation is earthed through gland.

0 Answers   HAL,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)