Wanted to send the Notification to the Supplier by e-mail.
Answers were Sorted based on User's Feedback
Answer / srikanth
At supplier site, mention the email id or on the PO when
you click on 'Approve' Button, a form opens, enable the
email check box and enter the Supplier mail id. Ensure
that the length of the email id is less than 50 characters
as per 11.5.9 version.
| Is This Answer Correct ? | 18 Yes | 0 No |
Answer / victor
In addition to above
You can send the PO after creation or approval by -
Use the PO Summary>Tool>Communicate functionality to send
the PO to any one by Email Address.
| Is This Answer Correct ? | 5 Yes | 1 No |
Answer / vivek
PO can be communicated by using the std functionality as
mentioned in above answer.
for any other type of notifications, ex- delay supply,
rejection of material, RFQ's we can use Oracle alerts.
This solves many requirements without using isupplier
modules.
| Is This Answer Correct ? | 5 Yes | 3 No |
Answer / viswanath
You have to set the Email as communication option in the
Supplier Site level. This would display the field when you
approve the PO.
| Is This Answer Correct ? | 3 Yes | 2 No |
Answer / kishore kumar
Suppose you need to send notifacation with additional
information, Then we can use UTL & SMTP Package, So that we
can send the variours information with the required
template format. Please reply if i am wrong.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / akshay
You can also have supplier role setup in iSupplier through
which you can send the emails to supplier without any
customization in Oracle Workflow.
| Is This Answer Correct ? | 0 Yes | 1 No |
After pick released, can I change into backorder? If it is possible, how?
What is the use of LC? How is it useful in export sales?
How many KFF are there in Order management? What is the use of Sales Order Flex-Field?
What are the steps required for settign min-max planning ????
1.Is it mandetory to recieve an expenses item,if we do not recieve what would be the PO status.? 2.Can we Open a closed PO.?If yes,How...?
Diff b/w Discrete mfg and Process manfactureing? If anyone have the detailed steps on this topic, please forward to me yakumar47@gmail.com
How do i generate Taxes when i'm doing Return To Vendor Transaction?
WHAT ARE THE DIFF TYPES OF CALENDERS IN R12 ??? PLS EXPLAIN THEIR FEATURES ????
in what case consultant will suggest for more than one operating unit, reasons?
Tell me is there a way to update schedule ship date for all lines of so in one go?
What is the item relationship and item cross relationship ???? what is the purpose of it ?????
In picking screen, what are the mandatory details to be entered?