v stands for verification and validation
It looks like "V"
in this model simultaneously testing is done along with
development
when requirements are gathered there is assesment of
requirement
after that preparing project plan and after that preparing
test plan
after that there will be designing simuteneouly there
will be design phase testing and after that coding there
will be program phase testing after that unit testing and
system testing at last there will be test effiency and
last port or deployment testing
Mail if i am wrong
sirisha
suryasirisha_k@yahoo.co.in
Is This Answer Correct ? | 1 Yes | 1 No |
Answer / saira
\ /
Bussiness Requirement User Acceptance testing
\ /
\ /
System Design System testing
\ /
Detailed design Integration testing
\ /
Code Unit testing
\ /
\ /
\ /
\ /
This is the 'V' model
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / preethi
V-Model is one of the SDLC process to follow.
Following is one of the v-model with all the possible
phases.This is generally using in all the possible corporate
level companies.
BRS SR and M
\ /
\ /
SRS UAT
\ /
\ /
HLD\LLD ST
\ /
\ /
SC IT
\ /
\/
BRS: Business requirement Specifications
SRS: Software Requirement Specifications
HLD: Higher level Design
LLD: Lower level Design
SC: Software Coding
ST: Software Testing
UAT: User Acceptance Testing
SR & M : Software Release & Maintainance
Regards
Preethi.G
Is This Answer Correct ? | 0 Yes | 3 No |
Why tester called as Bug and Dev.called as a Defect Why?Is there specific reason behind it.
What is Reproducible Defect? and When we will rise that defect as Reproducible Defect?
how can s/w QA process be implemented without reducing productivity?
I want to know all detail of v model phases
How would you determine the performance of a web application by looking at the values of ?Response Time? and ?Pages Per Second??
what is exit criteria and entry criteria with proper examples??? hi, i faced so many interwies in this question...so plz answer this questions as early as possible...
What are the drawbacks of manual testing?
Is anybody have the telecom systems test cases from start to end?
Difference between Agile process and V Model
What is Risk Mitigation and who will involve in Risk mitigation plan?
How do you debug SSH?
What is smoke test? Do you use any automation tool for smoke testing?