This measurement is the value of the work that's been completed to date:
A. PV
B. AC
C. EV
D. EAC
No Answer is Posted For this Question
Be the First to Post Answer
You do not expect the types of variances that have occurred on the project to date to continue. If BAC = 300, ETC = 275, PV= 300, AC = 200, EV = 250, and CPI = 1.25, what is the EAC? A. 240 B. 250 C. 475 D. 150
When a project is being performed under contract, the product description is provided by which of the following? A. The buyer B. The project sponsor C. The project manager D. The contractor
Which of the following describes the Executing process? A. Project plans are put into action. B. Project performance measurements are taken and analyzed. C. Project plans are developed. D. Project plans are published.
What are the Initiation process outputs? A. Project charter, historical information, and project manager identification and assignment B. Project charter, project manager identification and assignment, constraints, and assumptions C. Project charter, historical information, constraints, and assumptions D. Project charter, constraints, and assumptions
HI everyone, I am commerce graduate, completed MBA Finance in Distinction. I would like to do FI/CO. Could any one of you please suggest, which is the best instistute for FI/CO training in Hyderabad. Compulearn, Reliance, or other. Thanks in advance Rupa Gupta
what is software project planning?
What are the tools and techniques used in the Initiation process? A. Project selection criteria, historical information, expert judgment B. Project selection methods, historical information, expert judgment C. Project selection criteria, expert judgment D. Project selection methods, expert judgment
You have been asked to submit a proposal for a project that has been put out for bid. Prior to submitting the proposal, your company must register so that their firm is on the qualified seller list. Which of the following is true? A. The qualified seller list provides information about the sellers and is a tool and technique of the Solicitation process. B. The qualified seller list provides information about the project and the company that wrote the RFP and is an input to the Solicitation process. C. The qualified seller list provides information about the project and the company that wrote the RFP and is a tool and technique of the Source Selection process. D. The qualified seller list provides information about the sellers and is an input to the Solicitation process.
You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. Customers must pre-register before being allowed to order wine over the Internet so that legal age can be established. You tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following? A. Preferential logic B. Soft logic C. Discretionary dependency D. Hard logic
You are working on a project that will upgrade the phone system in your customer service center. You have used bottom-up estimating techniques to assign costs to the project activities and have determined the cost baseline. Which of the following is true? A. You have completed the Cost Estimating process and now need to complete the Cost Budgeting process to determine the project's baseline. B. You have completed the Project Plan Development process and established a project baseline to measure future project performance against. C. You have completed the Cost Estimating process and now need to complete the Project Plan Development process to establish a project baseline to measure future project performance against. D. You have completed the Cost Budgeting process, and the cost baseline will be used to measure future project performance.
You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery score chain. You have your activity list in hand and are ready to diagram the activity dependencies using the PD technique. You know that: A. PDM uses AON diagramming methods. B. PDM uses AOA diagramming methods. C. PDM uses ADM diagramming methods. D. PDM uses PDM diagramming methods.
Why do you want to switch over from IT to management?