A building wall is to be constructed , its 12 ft high and 40 ft long and labour cost per foot is 100 rupees , tell me the total cost of labour for that building work plz explain answer ..I am hurry plz any one give me ans as immediately as possible Thanx
Here , the cost will be charged on the basis of per ft square . Total area covered 40 × 12 = 480 .
As per ft required cost is 100 ,hence for 480 square ft ,total labour costs will be 480 × 100 = 48000 rs
Is This Answer Correct ? | 1 Yes | 0 No |
What is the difference between Fe500 and Fe500D rebars in their appearance and also is there any change in their Yield Strength of these rebars?
As an engineer, what u should do when the construction of a building doesn't meet the required specifications?
convert area- 1 war = meter, 1 guntha = meter
As we know that steel is a tension member but why we are using STRUCTURE STEEL as a COLUMN (Without concrete) where column is a compression member and compression strength of steel is very low
how much steel and concrete required for 450 sft slab? tell also the method
How can we make a hole in a solid rectangle using solidsworks?
1.(a.) how do you calculate the volume of mortar for 1 piece of block 450mm x 225mm x 225mm. (b.) calculate for 1sqm
How to calculate soil bearing capacity of soil?
Basic civil interview questions
Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? Regards,
45 Answers CDS, L&T,
what is the percentage of binding wire required for 1 mt of steel binding in gerally
How manu days after the casting of a slab another slab can be casted above it? what is the total curing time of a slab if ponding is not done on it?