Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


A building wall is to be constructed , its 12 ft high and 40 ft long and labour cost per foot is 100 rupees , tell me the total cost of labour for that building work plz explain answer ..I am hurry plz any one give me ans as immediately as possible Thanx



A building wall is to be constructed , its 12 ft high and 40 ft long and labour cost per foot is 100..

Answer / pritamdebnath

Here , the cost will be charged on the basis of per ft square . Total area covered 40 × 12 = 480 .
As per ft required cost is 100 ,hence for 480 square ft ,total labour costs will be 480 × 100 = 48000 rs

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

how much kg of binding wire is used in slab ?

4 Answers   L&T, Standard,


Ratio of cement : sand for fixing slab and tiles in the floor and also quantity of cement and sand requires for laying slab and tiles separately (area 100 sq. ft)

1 Answers   DLF,


How to Calculate in measurement RCC Colo um Spred design for Billing

1 Answers   JMC Projects,


how much binding wire required per tonne slab beam columns

5 Answers   GMR,


How much cement and water required for cement selery????

0 Answers   Engineering,


whether earth to the height of 80cm could be filled in the basement inm place of jamuna sand

5 Answers   L&T,


how many shuttering material required for 1000 sq.m built up area.

0 Answers   ABC, CGHB,


What is full form of r.c.c?

1 Answers  


how to calculate the scour depth

0 Answers  


what is the stripping time of beam column & slab?

2 Answers  


For a RCC section with congested reinforcement , what is the compaction factor

3 Answers   Arihant, GMR, Gulf International Contracting, NBCC,


How do you calculate the power of a centrifugal pump?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)