what is Pre- commissioning.

Answers were Sorted based on User's Feedback



what is Pre- commissioning...

Answer / mahesh

Before start up a plant need to cheek instrument range, connection, parameter, soars. different cheeking only help of p&id.

Is This Answer Correct ?    2 Yes 0 No

what is Pre- commissioning...

Answer / raja2016

In addition to above ans w. r.t an instrument...

w.r.t to a system consists of PLC panel
Earthing should be done properly and proper earth resistance value...
Electronic earthing and body earthing..

UPS supply availability, all the cables.,
PLC-MCC
PLC- field
ensuring laid,terminated and loop checked okay...

PLC- SCADA PCs all Ethernet cables laid and terminated as per system architecture...

Is This Answer Correct ?    1 Yes 0 No

what is Pre- commissioning...

Answer / s93381

before the plant startup check all system instrument parameter that is Pre- commissioning.

Is This Answer Correct ?    0 Yes 0 No

what is Pre- commissioning...

Answer / faiyaz

before start up the plant we check all the instrument and parameter with the water in process line that is called pre commissioning

Is This Answer Correct ?    0 Yes 0 No

what is Pre- commissioning...

Answer / faiyaz

pre commissioning is the process of providing the ability of a pipe line and piping system to contain product without leaking

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Instrumentation Interview Questions

what are the definitions of input, output, command & signal according to instruments controlled by PLC using DCS System?

0 Answers  


What is the difference between PLC and DCS?

4 Answers   Honeywell,


What is the meaning of wet leg

0 Answers  


describe yourself?

1 Answers   TCS,


What is SLPC & MLPC? How it works?

2 Answers  






what's the minimum level required of SIL (safety integrity level)to use fire and gas system?

2 Answers   L&T,


Which standard of hazardous area classification used in India?

1 Answers   Orchid,


what are the documents(Construction point of view for a process plant) submitted by contactor initially entering in to new site for client?

0 Answers   NTPC, PSU,


What is first echo & echo window in radar type level transmitter?

0 Answers  


How to calibrate DP transmitter by using HART communicator ?

1 Answers  


IS there any effect of vortex in low pressure side of the transmiter after the orific in feed water line? if yes then what is the calculation?

0 Answers  


what is compensation? temprature & pressure

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)