how to know the one way or two slab

Answers were Sorted based on User's Feedback



how to know the one way or two slab..

Answer / brijesh p yadav

If Ly/Lx is less than or equal to 2 then it is one way slab.Similarly if Ly/Lx is Greater than 2 then it is Two way slab. (Where Ly=Longest side of slab, Lx=shortest side)

Is This Answer Correct ?    21 Yes 13 No

how to know the one way or two slab..

Answer / siva sankar

When ly/lx less than 2 than the slab will be two way slab vice versa..

ly/lx>2 one way slab &
ly/lx<2 twoway slab.

Is This Answer Correct ?    3 Yes 0 No

how to know the one way or two slab..

Answer / vipul ghade

When the ratio of ly/lx is less than 2 or equal to 2 then two way slab
And when ratio of ly/lx is greater than 2 then one way slab

Where:- ly = longer side of slab .
lx = shorter side of slab.

Is This Answer Correct ?    2 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

What do you mean by bond? What are the different types of bonds?

0 Answers  


what is the use of beam end forces while using a staad ? wha they are show

0 Answers  


what is the code provision for acceptance of fineness modulus range for fine aggregates in design mix

1 Answers  


SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?

0 Answers   HCC, Supertech,


1. HOW MUCH CEMENT AND SAND REQUIRED TO PLASTER 100 SQM WALL. 2. HOW MUCH CEMENT AND SAND REQUIRED FOR SCREED WORK OF AREA 30 SQM

0 Answers   Civil Service, Intelinet, Marg, PMC,






what is the meaning of M & 20

5 Answers  


What are the different types of civil engineering?

0 Answers  


what is the difference between 2 legged to 4 legged stirrups?

1 Answers   VRC Constructions,


What is quantity of Cement and Sand required for the 1 cum brick masonry with 1:6 Ratio cement mortar.

2 Answers   RPP Infra Projects, SIL,


what is the stripping time of beam column & slab?

2 Answers  


questions with answers to face an interview of an civil engineer regarding RCC buidings

0 Answers   Horizon Computers, NBCC,


what cement consumction plaster 15mm think per sqmt 1:3&1:6 how much kg.

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)