How to calculate the dia of reinforcement when required (as per drawing) dia of reinforcement steel not available at site?

Answers were Sorted based on User's Feedback



How to calculate the dia of reinforcement when required (as per drawing) dia of reinforcement steel ..

Answer / rana zafar iqbal

0.00616 x d x d

0.00616 x 10 x 10 = 0.617 is the weight of 10 mm dia bar

Is This Answer Correct ?    7 Yes 1 No

How to calculate the dia of reinforcement when required (as per drawing) dia of reinforcement steel ..

Answer / vivek gupta

This formula we calculate s1.d1^2=s2.d2^2

Is This Answer Correct ?    5 Yes 1 No

How to calculate the dia of reinforcement when required (as per drawing) dia of reinforcement steel ..

Answer / engr saleem mughal

calculate weight of 1 ft steel and then calculate dia of steel by this formula.
d= sq.root of weight/0.7854*1.52

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

How much quantity of rod binding work by a rod binder per day

0 Answers  


Howmuch bend to be provide for 200/600 BEEM

0 Answers  


Mujhe koi ye bta do ki 1.54 hi ku lete h material ki quantity niklne ke liye Sab jgha dhund liya bt samj nhi aaya mujhe koi alag aalag krke smjao ki cement m aggr. Dust m itne % wet or dry % hoti h fir kaise kaise 1.54 aaya kha se aaya smjao koi pls m confuse hu my calling nd wts app no. Is +919034604938

2 Answers   ADP,


how much sand requires for Light weight blocks for 100sqft

1 Answers   Bahria Town, NCC,


Why there is no use of sea water in producing electricity

20 Answers   Infosys,






I s code of steel

6 Answers   Cicon Engineers,


what is the criteria for placing reinforcement in footing and slabs e.g which span have to place first.

4 Answers   Al Futtaim Carillion, NTPC,


I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

0 Answers  


how do you stabilize a waterlogged area in road construction

0 Answers  


What is the difference between EPC,DBOOT and BOOT.

2 Answers   IVRCL, NHPC,


What is the ratio of cement, sand, aggregate of mix M25

20 Answers   CCCL, Sarvottam Cement,


What is the meaning of unit weight of cement?

2 Answers   L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)