How many bricks required for 1 cu.m

Answers were Sorted based on User's Feedback



How many bricks required for 1 cu.m..

Answer / sfz

500 nos (0.19m x 0.9m x 0.9m ) brick size

Is This Answer Correct ?    20 Yes 4 No

How many bricks required for 1 cu.m..

Answer / ramesh.

580nos(0.23mx0.10mx.075m)size

Is This Answer Correct ?    11 Yes 6 No

How many bricks required for 1 cu.m..

Answer / mohammed muktadeer

size of brick 9"x4"x3" = 0.2286mx0.10mx0.0762m = 0.00174 volume of brick
brick required for 1cubic meter =1/0.00174= 574.7bricks

Is This Answer Correct ?    1 Yes 0 No

How many bricks required for 1 cu.m..

Answer / dinesh koli

500nos. required (0.20×0.10×0.10cm) size brick

Is This Answer Correct ?    3 Yes 3 No

How many bricks required for 1 cu.m..

Answer / chandan kumar singh

1/(.20*.10*.10)=500 nos bricks.

Is This Answer Correct ?    1 Yes 1 No

How many bricks required for 1 cu.m..

Answer / meer irfhan ali

530 nos (9"x4"x3") one brick size

Is This Answer Correct ?    0 Yes 2 No

How many bricks required for 1 cu.m..

Answer / prabhakar trimukhe

550 nos bricks are required in 1 cum and with cement mortor(.20x.20x.10 m)
without mortor 500 nos

Is This Answer Correct ?    0 Yes 5 No

Post New Answer

More Civil Engineering Interview Questions

what is the types of surveying?which type of survey carrying for type of work?

1 Answers  


how to calculate the steel for beams and columns for tender purpose? any formula have?

4 Answers   Ashok Leyland,


what is density of 20mm coarse aggregate.plz send answer my below adress e.mail

0 Answers   NG Constructions, Quaid-e-Azam International Hospital, Shafiq Constructions,


difference between specification and method of statement

3 Answers   L&T,


How much quantity a carpenter can do in a day

1 Answers  






why development length = 50D . why not 100D

0 Answers  


why are you joining in this (applied post) job and your aim for this job

0 Answers   APPSC,


what is mcArther pile?

1 Answers   Kerala Public Service Commission,


How to calculate 1 brss for RCC work  

0 Answers   Allied Group, Jyoti Structures Ltd,


What are the types of ladders?

2 Answers  


For making a new road in a village having a school & hospital , tell the steps of construction systemically ?

0 Answers   UPSSSC Uttar Pradesh Subordinate Services Selection Commission,


a simple instrument used for the measurement of colour in water is called

8 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)