how to calculate sand, aggregate and cement in m25 concrete?
Answers were Sorted based on User's Feedback
Answer / rohit singh
Grade m25= 1:1:2 , sum=1+1+2=4
Dry concretein 1 cum =1. 52
Cement =1. 52/4=. 38*28. 8=10. 94bags cement /cum concrete
Sand=1. 54*1/4=. 38cum
Aggregate=1. 54*2/4=. 76cum
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / narayan rijal
1.52/(1+1+2)*28.81=cement bags
0.41=sand
0.83+aggregate
| Is This Answer Correct ? | 3 Yes | 8 No |
I want to know about history of civil engineering?
what is the formula to find the diagonal shape stirrups?
calculate if the size of the beam is 300*500 then L for the top & bottom bar
how to calculate the cement, sand, coarse aggregate required for one cubic meter of concrete?
how to calculate weight of round steel bar and square steel bar, i section bar and c channel bar, angle bar
What is cutting Length of stirrups of a beam 300mm*300mm.
how much kg of binding wire is used in slab ?
what is the initial setting time & maximum duration concrete get hardening for ordinary portland cement?
silt maximum in sand.
What kind of foundations used in block cotton soils
What is Refuse Area ? And What is Definition ?
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)