Brick size 230X115X150mm, how many bricks, quantity of sand,
cement required to construct 10 sq mtrs of 115mm thick brick
wall.
Answers were Sorted based on User's Feedback
Answer / sha
Consider 1 cm mortar..
so the size is .24 x .16=0.0384
num of bricks is=10/0.0384=260 nos
Is This Answer Correct ? | 7 Yes | 4 No |
Answer / nirmala
earthwork excavation by manual means for foundation of buildings,culverts,water supply and sanitary lines and electrical conduits etc.either in pits or in trenches, in ordinary soil including dressing the bottom and sides of pits and trenches,stacking the excavated soil clear from edges of excavation with lead up to 50m,including breaking of clods complete as per specification ,including pumping of water,including cost of all labour,material,transport,hom of machineries,all lifts,loding and unloding .specification no KBS 2.1(a)/2.3.5.work to be completed as per the directions of the engineer in charge.
UNIT QUANTITY RATE(IN RS) AMOUNT(IN RS)
Cum 230 204 46920
please tell me the how its came quantity
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / sjtbehera
Brick size- 230 x115x50Consider 10 sqm - 10x.115=1.15cum 115mm th.
Normally mortar joint will be less than 1cm, taking 1cm mortar joint the actual th. Of wall thickness will be-.105mm
So, actual volume- 10x.105=1.05 cum.
No. Of bricks= 1.05/.23*.115*.150=264 nos. Take 5% wastage it comes around 280 nos.
Mortar requirement- total volume of brickwork- 1.05 cum
For fog filling, for use of cut brickwork, uniform joints take 15% extra
So total volume- 1.05+1.05*15%=1.2075
For dry volume, volume increase 1/4 th ofmortar so 1.2075+1.2075/4=1.509 cum
So for 10 sqmt 1.509 cum mortar
If you take 1:6 then you calculated cement and sand
1.509/7=.215 cum
Sand=.215x76= 1.29 cum
Is This Answer Correct ? | 6 Yes | 17 No |
What is the Allowable silt content of sand for construction purposes?
difination of civil engineer
What is the yield of 100 litres of water and 10 kg of cement in grout mix?
Q:What is the formula of bar to bent the slab in bent slab? Second question Q: what is formula to calculate the hook?
Please give a brief description of centre of gravity
actually dia of the bar reduce asper drawing spacing also decrease that time so how to calculate the spacing of with respect to changed bar dia?
how to calculate sump capacity
2 Answers AVS, KMC, Personal Assistant, Shrey Associates,
what is unit of density,specific gravity
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
lap lenth
can u use instead of water milk for concreting
what is mean by tremie concrete