Answer / warren holden

Increasing P (proportional gain) will result in faster,
more aggressive, control dynamics with potentially more
overshoot and longer settling time to steady state
condition in the closed-loop response (assuming that I
(integral action time) and D (derivative action time)values
are held constant whilst P is increased).

Is This Answer Correct ?    3 Yes 0 No

Post New Answer

More Instrumentation Interview Questions

How to calculate the Range of level transmitter ?

1 Answers   CPCL, Sejong, SSPL,


what is the difference in Kg/cm2 and mmwc?

2 Answers   Niko,


Sitrans LR460 Radar level transmitter getting level out or disturbed level during moisture present in the material ie coal in the pccb bunker in CHP.Any suggestions for this problem...????

1 Answers   ABG Shipyard,


WHAT IS MEANT BY PROJECT MANAGEMENT STRATEGIES IN INSTRUMENTATION?

0 Answers  


In split range control, we will control 2 outputs with time interval. Eg :(with 4-20 ma signal, for 4-12 ma we are operating one control instrument like valve & for 12-20ma we are operating other control instrumet (other valve). If we get a signal of 15ma to first instrument (Valve 1), what will happened to the first valve, and if we get signal above 20 ma to 2 valve what will happened ?

3 Answers  






what is Analog input/output & Digital input/output,

2 Answers   Bapco Bahrain Petroleum Company,


what is KV and XV valve

0 Answers  


the 3 most common transmitter protocol being in refinery or qatar gas and aramco.

0 Answers   Shell,


How does a redundant controller comes in line when the main controller fails??

3 Answers   Yokogawa,


what is air to open and air to close control valve and difference btwn this...and how to measure milli amp by this...and what is the role of positioner and i/p converter in this..plz help me

2 Answers   HCL, SOC,


can we use a control valve without positioner

19 Answers  


why we use cascade control and feed foreword control in 3 element control of boiler drum ?what is feed forward and cascade control system ?

0 Answers   Visa Steel,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)