Answer / nilesh

Normally there is a P&I( Process and Instrumentation)
diagram not E&I diagram.In P&ID circle symbole related to
field mounted instrument while Square box with circle
inside is related to function in DCS.There is number of
other symbole in each catagory.

Is This Answer Correct ?    9 Yes 0 No

In E&I diagram what is the meaning of rectangular box and circular box..

Answer / ganesh prajapati

In P&ID, ESD signal is represented by a triangle with ESD
mentioned inside a triangle.

Is This Answer Correct ?    1 Yes 0 No

In E&I diagram what is the meaning of rectangular box and circular box..

Answer / d das

ok mr. nilesh. but which one is ESD signal how should we
know? in a P&ID drawing.

Is This Answer Correct ?    1 Yes 1 No

Post New Answer

More Instrumentation Interview Questions

What is the difference between pt100, pt500 and pt1000 RTDs?

3 Answers   ICI Pakistan,


whats diffeence between dcs & scada operation.

3 Answers   Orchid, Reliance,


how to calibrate any tansmiter by loop or hart calibrator

2 Answers  


why we go for pcbs

2 Answers  


how to check electrical health of vibration probe?

1 Answers  






What is the working principle of oxygen analyzers(zirconium oxide type) used in CFBC boilers?

3 Answers   Bajaj, Kohinoor, Wartsila,


What is difference between sensors and transducers?

2 Answers  


full process of gas turbin?

0 Answers  


what is difference btween rotameter and orifice plate?

3 Answers  


difference between dcs & pld

2 Answers  


Hi i am aneesh, done btech in applied electronics & instrumentatiin. And then i took mba in finance & marketing.After that i got placement in finance co and worked there for 3.5 yrs.Now i wanted to come back to engineering job.But without engg experience, i may not able to find an opening.i have done a course related to flow meters and ite calibrations. Kindly suggest where should i try to get a job?

0 Answers   Qatar Petroleums,


What is the role of P(Protional), I(Integral) and D (Derivative) in PID Controller?

9 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)