what is the quantity of formwork in shuttering and
barbending is done by 1 mason and 1 helper
Answers were Sorted based on User's Feedback
Answer / rajesh n s
Shuttering/Formwork Workdone by 1 Carpenter + 1 helper is 5 to 7 Sqm / day
Barbending by 1 Barnender + 1 Helper is 80 to 100 kg / day
| Is This Answer Correct ? | 37 Yes | 5 No |
Answer / rajarshi basu
can u prove it technically how it is coming....or it is just based on site exp...
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / kamal mukherjee
Is the question technically correct ? General terminology of shuttering workmen is carpenter and steel fixer ins bar bender .
Again the output is linked to the type of the structure in execution.
Broadly Classified as : Sub structure or Super structure
Detailed Classification: Footing, Raft , Column, beam , slab , decorative work: Cantilever, loft, projection works etc..
general working is 2.5-3 sqm of shuttering and 700-750kgs for bar bending works for a pair of workmen
| Is This Answer Correct ? | 8 Yes | 7 No |
what is education Cess.
how much quantity required on weight of cement & on weight of sand for 1:4 ratio mortar?
what is called super elevation of the road?
I have used the proportion of cement:sand:gravel, is 1:2:4. cement and the sand was provided by the company but i provided the gravel. this combination was used to fill 500 cubic ft of wall. now i want to know how much gravel was used in making the wall. can you guys please help me?
Define polar co ordinates.
in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing
what is the use of water bar in water tank and is this an extra item in estimate?
what is escalation?how it is done?
where will u provide construction joint on slab?
6mm dia rod legth 1feet
I'm diploma civil engineer. My question is what better after diploma 1- BE/B.TECH 2.EXPERIENCE Pls.suggest.
What is the cost of Brickwall ( 4")(1:4) thick wall total Area 245 sqft with plaster(1:6). With all materials including.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)