What is the % steel required for a 3x3 slab.

Answers were Sorted based on User's Feedback



What is the % steel required for a 3x3 slab...

Answer / guest


RCC steel required for slab

= 0.5 to 1.0 % ( 40 to 80 kg/m^3

Is This Answer Correct ?    3 Yes 0 No

What is the % steel required for a 3x3 slab...

Answer / rupesh

% steel is 0.2 to 0.3%

Is This Answer Correct ?    0 Yes 2 No

Post New Answer

More Civil Engineering Interview Questions

Mixing of cement, sand & stone chips with oil will not give strength because ––

2 Answers  


length where bent up is made in slab of bridge from one end

0 Answers   NTPC,


How should we design a brick column and footing?(note: no reiforcement to be provided) Can you tell me any reference book where i could possibly find this design? Plz help urgently

0 Answers  


what is difference between active and passive earth pressure. how it effect the retaining wall design ?

4 Answers  


what is pmc(in rigid pavement)

1 Answers  






Please let me know the quantity of steel required for 2600 square feet 6" thick roof slab of the house?

1 Answers  


residential projects,structural.

0 Answers   Ambuja, KBR, Saudi Aramco Shell Refinery Company SASREF,


For 100 bag cement how i will calculate sand and metal aggregate.Mixing proportion 1:1.49:2.38

1 Answers  


manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.

0 Answers  


infosys campus ques... u drive a car,nmb of d car is KA17M8719. it leaves at10:26am frm davanager to bangalor which is264km away at a speed of 95km/hrCar reachs bangalor at 4:18pm. nw tel me wat is d date of birth of drvr

9 Answers   Ernst Young, Infosys,


what is the logical concrete mix design for M 30 Grade and the cement consumption per M3

7 Answers  


we have a bore well 275 depth & water is deliver at distance of 1000 feet from the borewell here iam not include the distance of depth and the deliver water horizontally at our reserviour tank on ground level

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)