Answer / ketan_k

1.cost saving
2. additiaon of fine prticle in concrete ,
3. to reduse heat of hydration
4. prolongation of setting time of concrete

Is This Answer Correct ?    14 Yes 0 No

Why use of fly ash in cement..

Answer / divyesh s mistry(pawan group)

1) REDUCE CEMENT CONSUMPTION WHICH DECREASE THE COST OF R.C.C.
2) SELF CURED MATERIAL SO LESS CURING REQUIRED.
3) GOOD FINISH SURFACE CAN ACHIEVE.
4) COMPRESSIVE STRENGTH SHOULD BE LOWER COMPARE TO DIRECT
CEMENT USAGE INITIALLY BUT CAN ACHIEVE REQUIRED STRENGTH IN
28-DAYS.
5) REDUCES THE HEAT OF HYDRATION SO THAT THE CRACKS CANNOT
DEVELOP.

Is This Answer Correct ?    12 Yes 0 No

Why use of fly ash in cement..

Answer / sumit

The target strenth is reached in minimum coast

Is This Answer Correct ?    4 Yes 0 No

Why use of fly ash in cement..

Answer / husen

main reson is reduce the cost of r.c.c and its use is
limte up to 20% by weight of the cemnt.

Is This Answer Correct ?    3 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

Plz tell how to find out stell bend correction for all angle of bend and in where it is? Plz answer

1 Answers  


Design a built-up column carrying an axial load of 1200 KN. Its length is 8m and it is effectively held in position at both ends and restrained against rotation at one end. Assume yield stress of 250 mpa

0 Answers  


WHAT IS THE %WASTAGES OF CEMENT, BRICK,TILES, STEEL,IN 1 M3,10M2,1 TON RESPECTIVELY

6 Answers  


how to calculate the steel quantity for beams & columns also footing net? what is the formulae for calculate the steel quantity? what is mean by (100.3)plinth level?what is mean by 100.3? explained it?

3 Answers  


how to find out the quantity of cement sand and aggregate in slab and flooring

1 Answers   L&T, Ramky,






What is the difference between pressure pipe and non pressure (NP) pipe?

1 Answers   Infosys, L&T,


Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.

0 Answers  


how calculate the ms beam weight?Please give me formula details?

4 Answers   KCC,


Why Vitrified tile are getting pop up.

0 Answers  


Soil bearing capacity formula

0 Answers  


what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?

0 Answers   L&T, PIPL,


how much steel required for 1 sq.m area?

12 Answers   L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)