How do we calculate the building footing calculation ?
Answers were Sorted based on User's Feedback
Answer / ds raju
Question is not clear. Is it design calculation ? or RCC
volume of the footing.
Design calculation depends on the safe bearing cpacity of
the soils and load on the footing.
Concrete volume can be calculated based on the shape of of
the footing.
For Rectangular/ square type : LxBxH
For Trepezoidal type : h/3 (Area at bottom-A1 + Area at top-
A2 +SqRt of (A1xA2)
| Is This Answer Correct ? | 36 Yes | 2 No |
Answer / r.vandhana
the calculation varies for each type of footing
| Is This Answer Correct ? | 24 Yes | 4 No |
Answer / sachin kesarkar
FOR RECTANGULAR FOOTING VOLUME= L*B*H
WHERE L=LENGTH B=BREDTH H=HEIGHT
FOR TRAPEZOIDAL FOOTING VOLUME=h/3(A1+A2+ROOT A1.A2)
WHERE h=HEIGHT A1=TOP SURFACE AREA A2=BTM.SURFACE AREA.
THERE ARE ALSO THE FOOTINGS WHICH ARE NOT PERFECTLY
TRAPEZOIDAL, IN THAT CASE WE HAVE CALCULATE IT WITH
TRAPEZOIDAL HAVING 5% VARIANCE.
| Is This Answer Correct ? | 20 Yes | 4 No |
Answer / srinivasan
1) FOR RECTANGULAR OR SQURE PORTION L X B X H WHERE L=
LENGTH B= BREADTH, H= HEIGHT
2) TRAPEZOIDAL PORTION H/3 (A1+ A2)+SQRT (A1*A2)
| Is This Answer Correct ? | 9 Yes | 2 No |
Answer / guest
width of footing can be calculated as
w= 2*l + 30
depth of footing can be varied as soil change
| Is This Answer Correct ? | 3 Yes | 9 No |
Answer / guest
Dear friends generally we do this footing calculation like
this two method =
(A)1st method =i)1.500 m x 1.500 m x 0.500 m = 1.13 Cum.
ii)½ x ( 1.500 m + 0.250 m ) x 1.500 m x 0.200 m = 0.260
Cum. (B)2nd Method =i)(1.500 x 1.500 x 0.200)+ (0.250 x
0.250 x.0.250)= 0.460 Cum.
ii) ( 1.500 x 1.500)+ ( 0.250 x 0.250)/2 x 0.200 = 0.231
Cum.
( But I think it is not proper procedure so please you do
properly )
| Is This Answer Correct ? | 10 Yes | 33 No |
why do we not deduct volume of steel to find actual volume of concrete in practical???
what is difference between expansion and construction joint?
RCC colums of 15"X9" each, roof height 10.5'ft, total pillars 12 nons. Span between pillar to pillar is 14/20/20 length wise and 17/14 width wise. Total Slab area 2400 sft and plinth area is 1900 sft. beams are 12"X12". kindly calculate load factor per sqft.
2 Answers ABS Construction, L&T,
1)What is the total volume of aggregates required for 1cu.mtr.solid hard concrete? 2)What is total mass of wet concrte and dry concrete after 28 days of M25? 3) Is 28 days strength is the final strength of concrete or it gets increasing as the time period increses.? 4)What is the volumetric proportion of concrete grade of M25.M30,M35,M40
can we go for short rcc column without any steel rienfocement carrying truely axial load only???(No other load acting on it such as wind load,earthquake & lateral earth pressure)
how many bags of cement are needed to make a cement mortar of 1:3
5 Answers ABC, DBL, DHFL Dewan Housing Finance Corporation, VV, WADAN,
Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??
how to estimate the earthwork,earth-filling for an isolated foundation
rate analysis of shuttering
in the footings first which reinforcement bar has to be layed as per design criteria.
Deshuttering time for slab 6.15 meter
How much cum. Brick work can do by 1 madon
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)