How do u calculate Schedule variance? What is the formula?
Explain with Example
Answer / abhishek tripathi
Schedule Metrics are related to variations between the
planned (base lined) schedule and actual schedule. Schedule
metrics basically provide you with schedule variance for
projects – scheduled completion, actual completion date and
the number of days of variance.
Schedule Variance = (Actual Duration-Planned Duration) /
(Planned Duration) * 100
Is This Answer Correct ? | 4 Yes | 3 No |
Give an example of high priority and low severity,low priority and high severity ?
Why is it often hard for management to get serious about quality assurance?
steps for perfoming integration testing?
what is the entry & exit criteria of testing process?
6 Answers APC, MBT, Microsoft, Nortel, TCL,
Can you please anyone tell me what are the Risk analysis technics we can use?
I want appear the ISTQB fundation level in june '08. For this i require previous question sets or glossaries.pls email me if any one have previous question sets or glossaries. my mail id is- jayanta_bncoe@yahoo.com Thanks jayanta
Web 2.0 Style Software Testing Management System- any suggestions? I'm looking out for a Web2.0 based software with features which makes test management easy. The feature I expect to see are; dashboards, live updating, reporting and communication system.
what is Bottle Neck testing??
What are the metrics available?
What are the various tools you have used in testing process?
Automation testing regarding with qtp, explain the process of testiing the application with qtp????
What is difference between qa, qc and software testing?