How do u calculate Schedule variance? What is the formula?
Explain with Example
Answer / abhishek tripathi
Schedule Metrics are related to variations between the
planned (base lined) schedule and actual schedule. Schedule
metrics basically provide you with schedule variance for
projects – scheduled completion, actual completion date and
the number of days of variance.
Schedule Variance = (Actual Duration-Planned Duration) /
(Planned Duration) * 100
| Is This Answer Correct ? | 4 Yes | 3 No |
Who solves problems ? - A Wise Person or - A Clever Person please justify your answer.
How is Release Management is done in STLC. What are tools can be used for the same.
What are test driver and test stub and why it is required?
Diffrence b/w compiled module and shared repository?
can any body tell what are the roles of QA clearly plzzzz
How would you test an ATM Machine?
what is the difference between quality assurance and quality control
4 Answers BIPL, BJIT, Cap Gemini, SouthTech,
What are test driver and test stub and why we need them?
what is scalability testing?
Requirement Analysis – Rs1000, Code Review – Rs500, Review of User Documents – Rs600, Continuing Education Programs – Rs800, Design – Rs400, Then what is the Cost of Quality?
What is mr and what information does mr consists of?
Explain what is the rule of a "test driven development"?