For G+4 storied building having 76000 sft per each floor,
can you prepare schedule in such a way that structure
should be completed with in 41/2 months and finishing be
completed with in 51/2 months?



For G+4 storied building having 76000 sft per each floor, can you prepare schedule in such a way t..

Answer / sanjeev kumar jain

Definately Yes. We shall require all the detailed drawings
& specifications of construction first of all. Now we shall
arrange the activities of construction in a bar chart
manner with overlapping activities. We will have to asses
the magnitude of the most time consuming activities and
thus allocate max resources to these. By continious mix &
match combinations of time & resources, we can certailly
work upon a schedule which is required subject to the
conditions that the level of resources as required in the
planning part are actually available and there is no
ambiguity in overall action plan.

Is This Answer Correct ?    7 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

How many kilograms of 12 mm coarse aggregate required in cufic feet for one cubic meter of M25 grade concrete

1 Answers  


levelling least count

5 Answers   NCC,


How to calculate sand , cement quantity for 23mm thk brick work(10x10)

0 Answers  


How much quantity of coping is done per day by one mason in Rmtr?

2 Answers  


how to tie 10 legged stirrups

0 Answers   Khan,






what should be the strength of Concrete cube strength for 7 days, if the designed mix is M20?

12 Answers   HPCL, Shrestha Civil Engineering Construction Company Pvt. Ltd, Sri Avani Projects, Tata Projects,


whats the concrete mix design ratio for M 35

1 Answers   Rahman Industries, SPRRG,


If I want to lab 16 mm dia. bar with 20 mm dia bar with 40D lap length which dia.should I consider for lapping

12 Answers  


suppose we have a tendency to make a hole on the surface of the beam, than where we goes to make it?

3 Answers  


what is RFI.How to prepare for slabs and beams connecting works to be executed.give order of work to be done.

0 Answers   bscpl,


In a slab where does the Uniformly Distributed Load (UDL) act?

6 Answers   Crescent,


what is lap length? why it is required?

4 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)