For G+4 storied building having 76000 sft per each floor,
can you prepare schedule in such a way that structure
should be completed with in 41/2 months and finishing be
completed with in 51/2 months?
Answer / sanjeev kumar jain
Definately Yes. We shall require all the detailed drawings
& specifications of construction first of all. Now we shall
arrange the activities of construction in a bar chart
manner with overlapping activities. We will have to asses
the magnitude of the most time consuming activities and
thus allocate max resources to these. By continious mix &
match combinations of time & resources, we can certailly
work upon a schedule which is required subject to the
conditions that the level of resources as required in the
planning part are actually available and there is no
ambiguity in overall action plan.
Is This Answer Correct ? | 7 Yes | 0 No |
How many kilograms of 12 mm coarse aggregate required in cufic feet for one cubic meter of M25 grade concrete
levelling least count
How to calculate sand , cement quantity for 23mm thk brick work(10x10)
How much quantity of coping is done per day by one mason in Rmtr?
how to tie 10 legged stirrups
what should be the strength of Concrete cube strength for 7 days, if the designed mix is M20?
12 Answers HPCL, Shrestha Civil Engineering Construction Company Pvt. Ltd, Sri Avani Projects, Tata Projects,
whats the concrete mix design ratio for M 35
1 Answers Rahman Industries, SPRRG,
If I want to lab 16 mm dia. bar with 20 mm dia bar with 40D lap length which dia.should I consider for lapping
suppose we have a tendency to make a hole on the surface of the beam, than where we goes to make it?
what is RFI.How to prepare for slabs and beams connecting works to be executed.give order of work to be done.
In a slab where does the Uniformly Distributed Load (UDL) act?
what is lap length? why it is required?