how to calculate quantities of sand , cement & aggregate in
1m3 - M20 , 1m2 of 6mm/12mm/20mm plaster , 1m3 20cm/ 1m2 of
10cm brick wall, paint quantity for 1m2 snowcem and lime
painting?

Answers were Sorted based on User's Feedback



how to calculate quantities of sand , cement & aggregate in 1m3 - M20 , 1m2 of 6mm/12mm/20mm p..

Answer / v.purushotham

1. Grade of concrete M20 so ratio is 1:11/2:3
let volume of concrete - 1cum
total ratio- 1+1.5+3 = 5.5
cement = 1x1.54/5.5 = 0.28 cum so cement is =0.28x
1440Kg/cum = 403.2 Kg = 8.064 bags
sand-0.28*1.5= 0.42cum
aggregate- 2.8*3= 0.84 cum

2. plaster = suppose 12mm palster
consider 1 sqm ratio is 1:6
volume of concrete= .012x1= .012cum ( per 1sqm)
incrase 20% for joint, filling and wastage=.012*20%=.0144

calculate 1/3rd of mortar when
dry= .0144*1/3+.0144= .0192cum

summation of ratio = 7
cement= .0192/7=.00274cum
= .0789bags
sand= .00274*6=.0164cum

this formula applied for 6mm and 20mm also.
plaster area= paint area

Is This Answer Correct ?    89 Yes 26 No

how to calculate quantities of sand , cement & aggregate in 1m3 - M20 , 1m2 of 6mm/12mm/20mm p..

Answer / padmarajan

M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg.

For 1m3 of M20 (1:1.5:3)
Broken stone = 0.856 m3
Sand = 0.472 m3
Cement = 8.22 bag

Is This Answer Correct ?    15 Yes 3 No

how to calculate quantities of sand , cement & aggregate in 1m3 - M20 , 1m2 of 6mm/12mm/20mm p..

Answer / sjtbehera

1. Grade of concrete M20 so ratio is 1:11/2:3
let volume of concrete - 1cum
total ratio- 1+1.5+3 = 5.5
cement = 1x15.4/5.5 = 2.8 cum so cement is =2.8/.347=8 bags
sand-2.8*1.5= 4.2cum
aggregate- 2.8*3= 8.4 cum

2. plaster = suppose 12mm palster
consider 1 sqm ratio is 1:6
volume of concrete= .012x1= .012cum ( per 1sqm)
incrase 20% for joint, filling and wastage=.012*20%=.0144

calculate 1/3rd of mortar when
dry= .0144*1/3+.0144= .0192cum

summation of ratio=7 so cement= .0192/7=.00274cum
= .0789bags
sand= .00274*6=.0164cum

this formula applied for 6mm and 20mm also.
plaster area= paint area

Is This Answer Correct ?    57 Yes 49 No

Post New Answer

More Civil Engineering Interview Questions

what is water cement ratio in design mix and its percentage in concrete and mortar?

1 Answers   Jain Housing, Shivshakti Sugars, Tulip,


How much area will be covered in 1 litre of Velvet touch paint in normal wall condition

0 Answers  


1)What is the total volume of aggregates required for 1cu.mtr.solid hard concrete? 2)What is total mass of wet concrte and dry concrete after 28 days of M25? 3) Is 28 days strength is the final strength of concrete or it gets increasing as the time period increses.? 4)What is the volumetric proportion of concrete grade of M25.M30,M35,M40

0 Answers   AVS,


why we use minimum cement as given in IS mix design code

5 Answers   BARC,


How manu days after the casting of a slab another slab can be casted above it? what is the total curing time of a slab if ponding is not done on it?

6 Answers  






what is BOQ? BOQ IS US IN ESTIMATE

8 Answers  


What are segregation and bleeding?

0 Answers  


how to calculate the quantity of cement,sand and aggregate when the ratio of mixing is 1:2:3

0 Answers   Ajnara Group, Assosa University,


different types of footing. and difference between footing and foundation

1 Answers  


what is the logical concrete mix design for M 30 Grade and the cement consumption per M3

7 Answers  


what is superbuilt-up area in flats & how it is calculate?

5 Answers  


How is improve my knowledge in construction industries....

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)