how to syncronize two dg sets
Answers were Sorted based on User's Feedback
Answer / shri..
1) first start the both DG set.
2) Then check Phase sequence R,Y,B
3) check the LL voltage & LN voltage. (both DG voltage
should same)
4) Check The engine RPM (both engine RPM should same)
5) Check The Frequency (both DG Frequency should same)
6) Then close the both breaker.
7) then cross check the voltage,Frequency,RPM
Is This Answer Correct ? | 9 Yes | 1 No |
Answer / santhosh
DG Sets with equal Voltage, Frequence and RPM should be
connected to a single bus with equal polarity and phase
sequence. Both the DG's should be protected with protecting
devices like breakers.
DG's should be operated in such a way that is starting only
one DG should get ON and as the load crosses 75% of the
capacity of DG then the second DG should get ON.
This will help in minimisng the consumption of fuel, Load
sharing and improves the performance of DG.
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / satender
you have first of all Start stop the DG's in manual mode ,
then check the voltage biasing and speed biasing by running
it on load ( single unit ) . Then check the phase sequence
of DG's and then give the synchroniizing command
Is This Answer Correct ? | 2 Yes | 4 No |
can we check the resistance of earthing electrode while it is connected with the neutral of UPS system
PLease anyone can tell me CTUM-15 specification?
what is lxr?
HI,how to know that the MEGGER which i am using is working properly,reply....thankyou
Determine the minimum cable size for a 28A single phase final sub circuit originating from the distribution board supplied by three phase submain. The route length of the final sub circuit is 54 m. Assume 1% voltage drop in the consumer's mains. Submain specification: Cable: 50mm2 4 core V75 copper; Route length 42m; Maximum demand 135A per phase
draw singleline diagram of star to delta and dol starters
Differenciate between circuit wiring and sub main wiring with illustrations
How can we calculate the fault level of the distribution system knowing the percentage impedance of transformer & subsequent equipments.
Earth leakage relay basic knowledge principle
how is positive, negative, zero sequence is happen.. how is effect on 3 phase system
how to calculate the slowness and fastness of energy meter if we have different kw load for example (0.746 kw and meter rev constant 400 and we calculate the 2 rev in 30 sec) please explain the formula thanks
1 Answers WAPDA Water and Power Development Authority,
plz send me the syllabus or any sample paper for engineer trainee recruitment if any,on ravinder911@yahoo.com
0 Answers Bhel, Maruti Suzuki,