Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


Electrical Design specifications



Electrical Design specifications..

Answer / me

Greetings all,

iam working in an out door lighting design for our plant
and i calculated the total watt needed (sum of all lights)
= 53 kw, 220 volt

our power supply is 480V

so, I chosed a 75 KVA transformer dry type 480/220-127 V 3
phase 60 Hz

cable size from feeder to transformer primary = 50 mm2 (1/0
AWG)

cable size from transformer secondary to distribution panel
board = 125 mm2 (250 MCM)

distribution panel board main breacker = 250 A

So, are my calculations ok ? any changes or suggestions ?

thanks in advance

Is This Answer Correct ?    2 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

How to calculate the Efficiency of Chiller

0 Answers   Knight Frank, L&T,


why cont we short earth and N.......?

3 Answers  


does magnetic interlocking take place in an induction motor ?

2 Answers  


wts d diff b/w C.T. & P.T.?

9 Answers  


Explain Energy and Power signals?

0 Answers   UOG,


What is the meaning of BUS?

20 Answers   CII, KLG Systel,


what is the capacity of storing mass electricity.

1 Answers  


what happens when back feeding supply accidently collapses with normal supply ??? How?? [that is sometimes in a substation 11kv feeder if their ws long time permit work, back feeding supply will provide from nearest substation... if accidently after the permit work,they charged the feeder without removing back feeding wat will happen...?]

1 Answers   KSEB,


What is mean by % impedance of transformer? detail explanations expected.

1 Answers   FCUK,


why power generate in 33 kv it will be step down by 11 kv .

5 Answers  


in one substation we have two power transformers of 100mva,75mva capacity.statoin load is155mva.how much each tranformers share the load????

6 Answers   TNEB Tamil Nadu Electricity Board,


advantages & Disadvantages of Solar power system?

2 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)