Answer Posted / dhanush d
In a 3 phase induction motor,the magnitude of the induced emf depends on the value of the slip.
At start a large emf is induced in the rotor circuit
Stator consequently draws a large start starting current which is 5 to 8 times the load value.
This may damage the motor as well as the components in line with it
Therefore,a Starter not only limits the starting current but also provides protection against low voltage and high load condition.
At the beginning the 6 ends of the three phase windings are brought out and connected as Star connection this reduces the voltage in each phase by 1 /√3 times the value it would,if it was in delta connection.
And tge starting current reduces to 1/3 of its value.
but the torque also reduces.
As this method is cheap, its used in mixers abd drills.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
difine electrical ballast in HPSVL
Where can I get Iidian straderd specifications for electrical items or works in web? please help me.
Define demand factor?
aternator every parts and its working
WHAT IS counter flux IN CT?
how net resistance islow in star connection and viseversa in delta connection...? if anybody could explain in detail it wud be helpful.
how to make an earthing certificate
how to decide choke rating for drive?
what is the difference between delta delta and star delta connection transformer? why we use delta delta transformer since it need earthing transformer for grounding?
Can anybody please refer the best and simple book for about Protection relays and in detail of all its protection ?
Please help me regarding my one concern. - During earth pit testing we noticed that the Clean earth pit and dirty earth pit showing continuity (Resistance value - 5ohm) . I want to know that if both earth pit have separate location and there is not internal looping between PIT then why such continuity is showing on it . Because of this issue the field side all earthing point showing short. In PLC panel we are providing two types of earthing cable which is coming from separate earth pit (Clean and Dirty earth pit) because of earth PIT showing short our PLC is not complying spec . please help regarding this issues.
Explain M Var? Which types of problem occurs when reactive power increase at the time of full load of plant and at the time of synchronize of plant?
According to conduit size which size wiring & how many wires can we provide wires in conduit & how can we select conduit size accordingly?
How generating electric power export to grid from the generating station ?
limitation of conductor height on ground when we consider EMC