I've one slab of 24m x 43m. How to calculate required steel
For this slab.
Answer Posted / saravanan
hi.
1) length of slab/spacing=no of bar lager side
2) width of slab/spacing=no of bars in shorter side
3) length of one bar = length of slab-(2*cover thickens)
4) length of one bar longer side*total no of bars in longer side(+)length of one bar shorter side*total no of bars=total length of bars requirement in slab
..weight of one meter bar =d^2/162
total weight of bars=total length of bar*weight of bar
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How to calculate the load of partion in flat slab if we use brick?
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
Why do you want to work here
which type of instrument included in plumbing work?name of instrument?
How to do rate analysis for concrete work including shuttering work?
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?
How many types bend used in civil reinforcing
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
Define Who designed the city of Washington DC?
what is idealized curve for concrere and steel
how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?
How to calculate canal slope curvature qty!
Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m
what is the water-cement ratio of mix design while 30mpa in 7 days?