Why attemperation is required in HRSG in a combined cycle
power plant?
Answer Posted / murali
for control steam temp and to avoid secondary super heater coil metal temp high. becoz secondary coil location is near flue gas out from gas turbine. this gas temp around 620 degree Celsius
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is surging in a centrifugal compressor ? How it occur's ? How is antisurging done ?
why do you consider yourself a suitable candidate for this position
what is the trip circuit supervision in an electrical meaning?
some one can tell me how residual type excitation is provided through transformers to an AC generator without any battery or PMG&excitor
operation
what is the difference between compensated & normal drum level in boiler drum?
why is the in steam turbine axial displacement of active side thrust pad is positive and non active side thrust pad is negative.
LAPT working in alternator / generator
can dp type level transmitter work in under vaccum condition
can u please tell me how to calculate the concrete quantity for a under reamed pile? r=300mm,depth=3m for a cylinder and for bulb l=.750mm,width=.525
what is natural frequency of turbine shaft .
explain how the third harmonic content of the magnetising current affects transformer design
DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.
By any way can we increase the B check hours from 300 to 500
How to calculate power press toneage