How much standard bricks required for a wall of 9*1200*1200 inches
Answer Posted / biplab sinha
Vol. of wall - (9/12)x(1200/12)x(1200/12) cum = 7500 cft
1 cft = 35.28 cum so vol. of wall = 7500/35.28 cum = 212.58 cum.
For standard first class brick 1 cum = 500 nos of bricks
Therefore total bricks required = 500x212.58 nos = 106293 nos
Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
What are the standard plastic limit/liquid limit/plasticityindex for differrent type of soils?
What is the density of 1:1.5 (Cement:sand) ratio in plaster? And Conversion in 12.5 mm thickness per square meter? Howmany Kg of Cement square meter in ratio of 1:1.5?
How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
what is the difference between replacement of cement by groundnut shell ash
One plate (women civil worker lifting Plate - Satti) sand measures how many cubic feet?
cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building
how i get all type of short type question answer about civil engg
que.is ideal size of bricnk use in india,joint size of mortar in massinary ,how many bricks used in 1cum.how to test at site.what is the possition of marka used in bricks?
what do you know that m20,m25
Reinforced concrete: suppose you are doing rough estimate for purchase of rebar for reinforced concrete slab for single stores residential building. You know total concrete volume will be 100 m3. How many tons rebar 6, 10 and 12mm will you require for the project?
please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)
why is the column design?
what is yield and tensile strength of steel, if steel has yeilding strength of 60 psi than how much its tensile strength?
pile load testing procedure