How to calculate the no of bags required for 12mm thick 1:6
plastering?
Answer Posted / goutam giri
Considering 100 sqm plaster.
Wet Volume of plaster =100X0.012 =1.2 cum.
Add @ 20 % for filling the depressions, joints, wastage, etc.=0.24 cum.
Total=1.44 cum.
For dry volume of mortar increased by ⅓ of volume =0.48 cum.
Total dry volume of mortar =1.92 cum
Volume of cement:-1.92/7 = 0.2742/0.0347 =7.9 bag
Volume of sand:-0.2742*6 = 1.6452 cum
Is This Answer Correct ? | 32 Yes | 4 No |
Post New Answer View All Answers
how to design and calculate materail quantity for concrete speedbreaker ?
Can we use the flyash bricks in brick bat coba?
How to estimate the shuttering material requirement for a slab and beam and shear wall..? Please send thumbrule to estimate material required ( Plywood, Ms plates, runners, acrospans, jacks)
What is the thickness of slab for 600 sq each) 2 slab construction. What should be the size of steel rod?
how much quantity of cement,sand and water required for 1 sq feet flooring work .
What is Base Shear ?
Why are steel plates inserted inside bearings in elastomeric bearing?
What are the advantages of building a dam on the river nile?
What is the use of extend command?
How to calculate the quantity of cement mortar 2" for mosaic tile fixing 12"x12"?
1. 1. The mass of a chunk of moist soil is 34 Kg and its volume is 0.012 cu. Meter. After drying in an oven, the mass reduces to 14.25 Kg. Determine the water content, the density of moist soil, the dry density, void ratio, porosity and degree of saturation. Take G = 3.25
What is bylayer?
how to take concrete quantity for precast segment for viaduct project?
Explain what is zoning permit?
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum