for 1sft of Cement plastering ratio 1:3 How much quantity
of cement and sand required.?
Answer Posted / gowtham1993
area of 1 sq ft
= 1'*1'*.06
=.06 cubic feet
cement sand ratio 1:3
so..... .015 cubic feet of cement
.045 cubic feet oh sand
| Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?
where will be the reinforcement of slab placed when there is an inverted beam and the bottom of the beam and slab are at same level ?
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
how to calculate the chair reinforcement length in slabs, footing or anywhere??
Floor to floor high of domestic building is 3m design a quarter turn staircase starting assume taken give a suitable diagram of it?
what is relation between SPT N value and driving piles after conducting a soil test?
what are the strength theories for yeilding and fracture materials. state the theory more suited for 1. mild steel or 2. concrete
PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg
all technical question
how water proof chemicals act in concrete to avoid leek?
Bitumen grades are 30-40,60-70, 80-100. what is mean by 30- 40
What is Time period of a building and its relation with frequency ?
sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.
design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal