what is civil engineering?
Answer Posted / m. jahir hussain
TOTAL VOLUME
1000 X 4" = 330Cubfeet
330/35.28 = 9.35 cubmeter
SLAB CONCRETE RATIO 1:2:4
1.57/7 = 0.2242
0.2242 X 1440 =323 KG CEMENT/M3
BAG IS 6.45 BAG OR 6.5 BAGS/M3
OUR SLAB VOLUME IS 9.35M3
9.35 X 6.5 = 60.775 BAGS OR 61 BAGS
| Is This Answer Correct ? | 8 Yes | 9 No |
Post New Answer View All Answers
sir i want to know that in L & T construction can we do our 6 months training proggramme cum placement???????
how to calculate number of bitumen for road asphalt
reinforcement slab, beam and column formulas?
how u design STAGING for Superstructure in BRIDGE construction?
What type of tensile strength is handling by crank in beam? Thanks.
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
how to calculate mivan shuttering matrial
Re: Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? please my email id is smgujjal@gmail.com
What should be the lap length in raft if height of raft is 0.800mm ...it couldn't b 50D or 40D...we just have to join upper and bottom reinforced...is there any formula for determine it...
what is the metal ratio in granular subbase coarse for one cum ? And please explain the morth table ...what is the difference between grading 1 , 2, 3 what it means..plz explain
how to calculate weight of 1.8 cum of aggregate
The concrete slump recommended for beams and slabs; is?
How to calculate thickness of MAT slab & Reinforcement? The dimention of under ground water reservoir is 80'X14'X 12 ft
What is the sugested procedure of water purification for public supply?
why we create short columns under grade slab?