In site how we can identify one way slab and two way slab?
Answer Posted / silambarsan
For easy identification without calculation,In oneway slab
main reinforcement provided in the shorter direction and
distribution will be longer side.In two way slab Both side
main reinforcement will be there and mainbar also act as a
distribution bar.
Is This Answer Correct ? | 41 Yes | 5 No |
Post New Answer View All Answers
types of survey and levelling instrument ?
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2
What is the difference in painting using Roller and Brush? What is the paint consumption difference? As per IS one coat of painting is painting from left to right and top to bottom whether this can be done using roller ( Roller Stick height and feasibility) ?
importance of the soundness test to determine the quality of cement use for any construction
what do you mean by yeild stress of a material? What will happen when hit is given to cement?
what r the precaution for high in atp tempareture,low in atp tempareture
How can i do RCC rate analysis?
what is the weight of 6000 psi concrete in lb/cft?
How to estabilish reinforcement Steel rolling margin for a building projects ?
Slump Values for works?
what is the theoritical percentage of concrete cubes testing per day?
What are segregation and bleeding?
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
The foundations are placed below ground level, to increase?