How to calculate cement and sand quantities in cement mortar
As 1:1,1:2,1:4,1:6 ?
Answer Posted / guppi chandra sekhar
Calculation of materials for 1cum of 1:6 Cement Mortar by
Volumetric method:
Specific Gravity of Cement = 3.15 ; Density of Cement =
1440kg/cum
Specific Gravity of Sand = 2.6 ; Density of Cement =
1550kg/cum @ 5% moisture
First of all we have to calculate yield of 1 cement bag
(50kg) mixed in 1:6
Volume of Cement = (50/1440) = 0.03472cum
Volume of Sand mixed = 6 X 0.03472 = 0.208cum (contains 5%
moisture)
Volume of only sand = 95% of 0.208 = 0.198 cum
Absolute volume of Cement = 50kg / (3.15X1000) = 0.016 cum
Absolute volume of sand = Weight of sand / (2.6 X 1000) =
(0.198 X 1550) / (2.6 X 1000) = 0.118 cum
Let volume of water added = 30litres = 0.03 cum
Moisture present in the sand = (0.208 - 0.198) = 0.01 cum
Total volume of water = 0.03 + 0.01 = 0.04 cum
Let, Moisture content in the mortar = 2% of yield
Let, yield = Y
(1-2%)Y = Absolute volumes of (Cement + Sand + Water) =
0.016 + 0.118 + 0.04 = 0.174 cum
Total Yield Y = 0.174 / 0.98 = 0.178 cum
1bag of 50kg Cement produces = 0.178 cum of 1:6 Cement
Mortar with 0.208cum of Sand @ 5% Moisture and 30 litres of
water.
Therefore, 1 cum of 1:6 Cement Mortar requires :
Cement = 1bag X 1/ 0.178 = 5.62 bags
Sand = 0.208 X 1 / 0.178 = 1.17 cum
Water = 30 X 1 / 0.178 = 168 .5 litres
Is This Answer Correct ? | 54 Yes | 21 No |
Post New Answer View All Answers
one steel fixers how much ton steel fabrication he will do same how much tone he will binding?
What is 1/8 on the architect ruler denotes?
To pcc 11 ft x 24 ft .How many bags of cement, sand and aggregate required? And for roofing how many cgi sheets required?
std penetration resistance in very stiff clays lies bet 2 & 4 4 & 8 8 & 15 15 & 30
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
at what pressure ply-wood is obtained by gluing wooden sheets
what is the difference between replacement of cement by groundnut shell ash
What is thumb rule for deep trench excavation
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
What do you meant by gui?
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
4. Differentiate between NC and OC soils. Draw curves for (i) Stress vs Strain (ii) Volume charge vs Strain (iii) Pore pressure vs Strain for these soils
In few lines, please be elaborative on extras and talents that make you a potential candidate for the post: