How to calculate cement and sand quantities in cement mortar
As 1:1,1:2,1:4,1:6 ?
Answer Posted / v.kapil
I think Mr. kamlesh is right
The considraion of voides for mortor is 25% and rest method
is same as our conventionel menthod, but for plaster 30 %
should be increase for undulation ( uneven wall surface)
also so total dry volumn is 1 + 25% + 30% = 1.55 Cum
Is This Answer Correct ? | 16 Yes | 15 No |
Post New Answer View All Answers
What are wooden shingles?
What is standard Sand? What is Regime condition? What do you mean by the core trench in Earthen Dasm? What is soundness test for cement? When negetive shear force takes place in a R.C.C member?
how to calculate MR 9(derivation)
what is the code provision for acceptance of fineness modulus range for fine aggregates in design mix
what is the meaning of 40/20 src
what is constat for brickwork
mean of NH4 pipe
What are the uses of layer?
What are the benefits of rcc pipes over steel designed pipes?
How to calculate the quantity of ingredients of M20 grade concrete?
HDPE pipe standard bends using for TSE irrigation? is it possible to use 30 degree?
I need model question papers for writing the Dubai municipality exam,for G+1
How long does it take concrete to harden?
What is the difference between Grade I, II and III of GSB?
design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal